When is a win a win?

Sept. 7, 2017

Addressing DOT liability concerning a subcontractor payment bond

Payment bonds on public projects are intended to provide a means of redress to unpaid subcontractors who cannot otherwise file mechanic’s liens against public property.

The procedures and case law that have developed around payment bonds have actually elevated the payment bond to the preferred method of recovery over breach of contract lawsuits and mechanic’s liens. For example, a prime contractor cannot escape liability to a second-tier subcontractor by merely asserting that it paid the first-tier subcontractor in full. Thus, you can imagine the disappointment when a subcontractor intending to file a payment bond claim learns that, due to oversight by the public entity, it failed to secure a payment bond from the prime or the bond is defective in some manner. This month, I highlight a case that addresses the liability of a public entity to a subcontractor when the public entity either fails to procure a payment bond or permits the bond to lapse. This case also is interesting because it represents a rare example of a court reversing itself and likely left the South Carolina Department of Transportation (SCDOT) wondering when a “win” really is a win.

Sloan Constr. Co., Inc. v. Southco Grassing, Inc., 2011 S.C. Lexis 355 (Oct. 31, 2011), involved a lawsuit filed by a subcontractor against a prime contractor and SCDOT in connection with a maintenance contract. This case went up on appeal to the Supreme Court of South Carolina—twice. The trial court determined that the prime contractor had failed to pay the subcontractor for work that was complete and free of defects. The court also determined that SCDOT failed to procure a substitute payment bond when it learned that the prime contractor’s surety had been placed in receivership. Nevertheless, the trial court ruled that SCDOT owed no duty to the subcontractor and thus that SCDOT was not liable to the subcontractor for its oversight.

On appeal, the Supreme Court of South Carolina sided with the subcontractor and held that the public policy underlying the South Carolina statute that requires payment bonds on public projects contains stronger language than most states’ “Little Miller Act” statutes. It thus held that subcontractors possess a private right-of-action against public entities that fail to “ensure that a prime contractor is properly bonded.” The Supreme Court remanded the case back to the trial court to determine the amount of damages.

After the trial court awarded damages to the subcontractor, SCDOT appealed the case back to the Supreme Court of South Carolina. This time, however, the Supreme Court embarked on an analysis of court decisions on this issue in other states. The court acknowledged that while most states refuse to grant a private cause of action against public entities for failure to procure a prime contractor payment bond, South Carolina should continue to do so for the same reasons it set out in the first appeal, namely that the South Carolina statute contained strong language favoring subcontractors. However, the court distinguished the failure of a public entity to procure a bond from the outset from those instances where the bond, for whatever reason, becomes void due to subsequently occurring events such as insolvency. The court reasoned that to hold public entitles liable in the latter instance is too onerous of a requirement. In a rare occurrence, the court essentially overruled its previous decision and held that governmental entities in South Carolina have no duty to a subcontractor to continuously maintain a bond once a valid bond is acquired.

You might think that SCDOT was relieved at this decision. It was . . . but only with respect to future cases. Despite its ruling on the law, the court held for the subcontractor in this case because the law set out in the previous appeal constituted “the law of the case.” In other words, when SCDOT filed the second appeal, the existing law, as set out in the first appeal, was that public entities are liable for both the failure to procure a bond and the failure to ensure a valid bond existed throughout the project. The court, in essence, honored its previous decision, but changed the law for future cases. Most courts across the country that have addressed this issue rule that subcontractors have no private cause of action against a public entity for their failure to procure or to ensure maintenance of valid bonds.

About The Author: Caudle is a principal in Kraftson Caudle LLC, a law firm in McLean, Va., specializing in heavy-highway and transportation construction. Caudle can be contacted via e-mail at [email protected].

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.