Trivia Tuesday, Nov. 24
Last week's answer
Question: Opened in 2010 to reroute U.S. Route 93 away from the top of Hoover Dam, the Mike O’Callaghan–Pat Tillman Memorial Bridge spans 1,060 feet across Black Canyon nearly 900 feet above the Colorado River. Because the sheer canyon walls and extreme depth made traditional bottom-up falsework or river barges impossible, how did civil engineers support and construct the twin cast-in-place concrete arch ribs before they met at the crown?
Answer: Temporary stay cables anchored to canyon rim towers held the segments in mid-air while a 2,500-foot high-line cableway hoisted materials.
Two unique 2,500-foot cableways were used throughout construction to carry workers and 45 tons of material and equipment into place. The cables hung from 330-foot-tall towers.




