Four beats to perfection

Feb. 2, 2018

Rehabilitation project rescues massive business center area on a tight timetable

So . . . how challenging can it really be to pave some parking lots?

Ubiquity and commonplace function serve to make such aspects of our infrastructure all but invisible—even as they are treated to the same pummeling use as all other forms of paved surfaces. A recent project in Mason, Ohio, that involved a series of large parking areas in a busy business center, as well as the ring road that feeds and serves them, exemplifies precisely how challenging rehabilitation and recycled pavement work can be, and as a result has earned a Roads & Bridges/ARRA Recycling Award.

First beat

The Mason Business Center (MBC) serves as a research and product development laboratory for consumer products. As the result of the closure of a nearby facility that would cause an expansion of the MBC, a facility-wide pavement rehabilitation program for the center’s existing asphalt pavement was conceived. An initial and overarching challenge would be that the facility would need to remain open and accessible during the entire construction process. In order to create and maintain an accelerated construction schedule, a comprehensive determination of subgrade soil conditions was performed in advance of recommendations for pavement design.

“We came on to map out pavement conditions and convert those to a pavement condition index score, based on the ASTM standard we follow that dictates how you collect certain defects in order to define and capture conditions and calculate them,” Mark Schmidt, CEO of Atlas 10, told Roads & Bridges. “We realized quickly there would be a significant amount of reconstruction needed on this job, at which point we engaged a geotechnical and pavements engineering firm to do a more thorough investigation of the subgrade, to verify our initial findings and supplement them with additional information on the subgrade modulus, so that we could make mix design recommendations.”

The overall project site consisted of 14 lots totalling approximately 63,200 sq yd, along with an access road of 2,000 linear ft. Based on the subgrade soil conditions in each lot, unique mix designs would be required, in order to stabilize the subgrade for extended pavement life. Consequently, Atlas 10 brought in SME, of Shelby Township, Mich., to assist with the geotechnical evaluation of the site.

Second beat

SME Senior Consultant Tony Thomas, P.E., looked at the MBC project as an exercise in anticipation: “We had to pre-emptively ask the right questions so we could vary or adjust accordingly, because there was just a three-month time period for this project.”

SME employed a nondestructive falling weight deflectometer to test the support provided by the subgrade to the pavement section, as well as determine how strong each pavement section was. That strength was then generated into a structural number (SN) for that section.

“What we found during testing was a pretty significant variation in the quality of the subgrade soil support,” Thomas told Roads & Bridges. “It was predominantly cohesive soils with varying amounts of sand, gravel, etc. But depending on the location of the overall site, it had different support characteristics. That could be due to how well it was compacted on initial construction, how much water got in there, how well was it protected from loading, equipment, other heavy weight like that. There’s a direct correlation with subgrade strength.”

The subgrade directly affected how each pavement section was going to be rehabilitated. Because the subgrade was variable and, generally, poor to very poor at supporting the pavement structure itself, and due to the tight construction schedule requirements, SME recommended full-depth reclamation (FDR) in many places.

“We took bulk samples across the entire pavement network, brought them back to our laboratory, and essentially assembled a matrix (see p 21) of the different pavement sections, thicknesses of material, amount of subgrade materials that would be incorporated into the stabilized mix profile,” Thomas said. “We ultimately generated five different FDR mix designs.”

Third beat

The reclamation, restabilization and paving of the lots and road would require multiple players.

“As far as the FDR/stabilization went, the soil conditions were a tough challenge at times,” Jim Zibble, project superintendent for Tenmile Creek Excavation, which was brought on to handle the FDR and soil stabilization, told Roads & Bridges. “We did have some rainy times, so there were mud issues to deal with but that’s what we do. There also were some very, very, very soft areas where our spreader trucks would sink in due to some drainage issues. But we got them stabilized and got them to specifications.”

Everything Tenmile utilized was on-site. “If there was 4 in. of asphalt and 4 in. of existing aggregate underneath,” Zibbel said, “we would take 12 in. total, the asphalt, the agg and several inches of subgrade as well, to make a mixture that worked with portland cement (PC). The subgrade was either sand or clay. If you’re using emulsion, you want it clean, but with PC you want some of that subgrade in there to give you a substance the cement will adhere to.”

Crews employed a Wirtgen WR250 stabilizer for the pre-pulverizing and stabilization work, as well as Terex spreader trucks and pneumatic tankers for the PC. A padfoot vibratory roller came up directly behind the stabilizer, and everything was sealed up with a Cat double-drum static smooth-drum roller. Once the site was balanced and graded to where it would end up, crews then spread PC on top of the reclaimed material and went back through with a water truck to get the PC to hydrate and provide the strength needed for the subgrade.

Fourth beat

Neyra Paving, out of Edendale, Ohio, came on to complete general earthwork and asphalt paving.

“We used a Trimble product to topograph the existing elevations and correct the grades,” Justin Neyra, president, told Roads & Bridges. “Then we took a Cat 120M2 grader with Trimble automation to do fine grading of the cement-stabilized areas.”

After adding or constructing much of the curbing on the lots, the wearing surface courses were ready. Neyra had to discriminate between the heavy-duty role of the access road and the relatively light duty of the lots themselves in layering the lifts. In all areas, the base course was a 19-mm PG 64-22 100% crushed aggregate, using 30% RAP plus Aramid fibers, while the surface course was a 12.5-mm PG 70-22 100% crushed aggregate, with 15% RAP plus Aramid fibers. Lifts levels on the road were slightly thicker than in the lots: 3 in. of base and 2 in. of wearing course vs. 2 in. of base and 1.5 in. of wearing course. A Cedarapids 362 paver was employed on the heavy-duty and wide open areas followed by a Caterpillar CB7 18,000-lb roller and a Caterpillar CB34 8,000-lb roller for compaction and finish rolling. On the smaller, tighter areas, a Lee Boy 8515 paver followed by Caterpillar CB34 rollers were used for compaction and finish rolling. Density requirements were significant—94% for the base and 98% for the surface—but were achieved.

All told, the MBC project came in $782,000 under budget and on schedule.

“We took the variability out of the construction process by assessing the site beforehand,” Thomas concluded. “We had a fine, well-tuned machine between the contractor, the testing firm and the pavers. You need that to make sure once you start, you won’t half-stop.”

The Mason Business Center Rehabilitation Project also was recognized as a demonstrator site by the U.S. Green Building Council, due to the sustainability achievements made during construction.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.