No. 10 - I-85 Yadkin River Bridge Design-Build

Dec. 15, 2014

The new dual bridges span a wetland, river and three

railroad tracks. To maximize effi ciency of the bridge

design, the team chose a modifi ed 77-in.-deep bulb-tee,

prestressed concrete girder for all concrete spans. To

eliminate the need for bridge overhang falsework, the

team implemented a special “edge girder” that also served

as the formwork for the deck slab overhang. The team

discovered by slightly widening the median of the bridge

to 70 ft that a single work bridge could be constructed in

the center median, reducing project cost, timeframe and

environmental impacts.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.