Future I-10 interchange nears completion in Avondale, Arizona
April 17, 2020
Work on interchange and bridge to finish later this spring
Motorists who use I-10 west of Loop 101 in the Avondale area of Arizona, near Phoenix, have been watching progress being made on a future bridge and interchange at Fairway Drive.
According to the Arizona DOT (ADOT), the bridge will be completed this spring as part of ADOT’s $20.8 million project to add the Fairway Drive interchange under the Regional Transportation Plan that Phoenix-area voters approved in 2004.
Crews recently poured the concrete deck for the Fairway Drive bridge over I-10. Work now is focused on adding safety barrier walls to the structure. On- and off-ramps for the future interchange have already been in use as detour routes for traffic at times when I-10 closures have been needed for bridge construction.
Other work to be completed over the next month includes resurfacing I-10 between Avondale Boulevard and Dysart Road with a new top layer of smooth rubberized asphalt. Crews also will finish installing lighting and traffic signals.
The city of Avondale is designing a Fairway Drive connection to the interchange and plans to start construction when ADOT completes its work on the I-10 project.
Funding for the Fairway Drive interchange project is provided by the Maricopa Association of Governments (MAG), which schedules regional freeway projects. ADOT says a primary funding source for MAG’s Regional Transportation Plan is a half-cent sales tax in the Phoenix area.