Cranes set beams for bridge project over Chagrin River in Ohio

Nov. 2, 2020

To perfectly execute a crane lift, planning begins long before the rigging is ever connected to the workpiece. A recent bridge project in Waite Hill, Ohio, east of Cleveland, amply demonstrated this reality.

The bridge was to span the Chagrin River in a valley between two hills, surrounded by dense forest and utility poles. ALL Erection & Crane Rental of Cleveland, a member of the ALL Family of Companies, was to provide two cranes to set box beams for the bridge. The site posed three distinct challenges in the form of limited access to the site, soft ground, and a tight or obstructed work space. ALL had the knowledge base to determine the best course of action, the broad fleet from which to draw the proper machines needed, and the experienced operators to execute the plan.

There was just enough room on either side of the river to position the two cranes, but not much room for anything else. This meant no lay-down area for crane assembly, so each piece would need to be trucked down the hill one at a time as the cranes were put together.

Being so close to the riverbank, the earth was soft, requiring special consideration for ground bearing pressure. Several tons of stone were trucked in to strengthen the ground capacity and more evenly spread the load.

The close quarters created by the trees and utility poles further limited maneuverability on the jobsite. 

Mike LiPuma, sales and rental manager for ALL Crane, was in charge of the job and sought counsel from two of his cohorts, project manager Chad Rados and sales rep Brian Meek. Together, the three men have more than 75 years of crane experience.

Positioned on the north side of the river was a 500-USt Liebherr LTM 1450-8.1 configured with 139 ft of main boom and 295,400 lb of counterweight. On the south side was a 550-USt Grove GMK7550 with 147 ft of main boom and 264,500 lb of counterweight.

Because of the site’s space and access limitations, the box beams—ranging in size from 85 ft long and 86,000 lb to 100 ft long and 100,000 lb—could only be trucked to the north side of the river. The LTM 1450 picked and set the first group of 100-ft beams, placing them on the north side abutment and a pier in the Chagrin River. 

“We chose the LTM 1450 because of its VarioBallast system, which reduces the ballast radius by allowing the counterweights to ‘suck in’ as the boom is swinging,” LiPuma said. “With the nearby trees and utility poles, this capability was vital to allow us to pick and set the beams in close proximity to the obstructions.”

After all the 100-ft beams were set, the 85-ft beams needed to be set on the south side abutment and the pier. Because the beams could only be trucked into the north side, the LTM 1450 had to pick the 85-footers and hand them off to the GMK7550, on the south bank, for final placement. “The 1450 would set a beam on the pier and cantilever out far enough to where the 7550 could grab it,” LiPuma said. 

“This job took a lot of planning,” LiPuma added. “But when our operators arrived at the site and gave everything a thumbs-up, I knew they were at ease and we’d created a safe, effective lift plan.”

Editor's Note: Scranton Gillette Communications and the SGC Infrastructure Group are not liable for the accuracy, efficacy and validity of the claims made in this piece. The views expressed in this content do not reflect the position of the Roads & Bridges' Editorial Team.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.