Virginia Department of Transportation takes another leap toward open government

July 1, 2005

The Virginia Department of Transportation (VDOT) is taking open government to a new level by providing the public online access to monitor the agency’s business performance. By a click of a button on the Internet, you can find out how VDOT is spending tax dollars on building, maintaining and operating 57,000 miles of roads and bridges across the state.

The Virginia Department of Transportation (VDOT) is taking open government to a new level by providing the public online access to monitor the agency’s business performance. By a click of a button on the Internet, you can find out how VDOT is spending tax dollars on building, maintaining and operating 57,000 miles of roads and bridges across the state.

Since March 2003, you could access the online Dashboard, which instantly shows the status of VDOT’s construction projects. Toady, the Dashboard has expanded sixfold by showing the latest performance of all other core business areas, including road maintenance, plans, studies, safety, finances, operations and environmental compliance.

“With VDOT spending about $3 billion of public money every year, taxpayers have a right to know how their money is being used,” said VDOT Commissioner Philip Shucet. “Increasing the level of transparency is absolutely essential for the success of VDOT to improve its bottom line. The closer citizens can watch us in all areas of our business, the better we will do.”

Visit the VDOT Dashboard at www.ViginiaDOT.org and see the agency’s daily performance in the following areas:

Construction - On-time and on-budget performance with projects under construction and completed projects

Maintenance - Repaving projects, bridge repairs and bridge conditions

Engineering - Studies, projects in the design phase and others that are ready to award for construction

Finances - VDOT’s spending and revenues

Safety - Crashes and fatalities on Virginia’s roadways

Operations - Current view of road construction, incidents and road conditions, including traffic cameras

Environment - VDOT’s performance with environmental compliance on projects

The Dashboard has served as an early warning system for project managers to get their projects back on track since early 2003. As a result, VDOT’s performance with delivering projects on time and on budget has greatly improved. Four years ago, the department completed fewer than 20% of its projects on time and 81% within budget.

“The extended Dashboard sheds more light on government business by letting the public see what is going on in VDOT’s key business functions where most of the tax dollars are spent,” Shucet said.

Sponsored Recommendations

See how fiberglass conduit stacks up to the competition in crucial areas like weight, corrosion resistance and installation cost.
Bridge construction projects are loaded with details and electrical conduit is a key component. Lightweight Champion Fiberglass offers lower materials and installation costs. ...
Investigators look to see if tragedy could have been prevented
Champion Fiberglass has provided a durable, cost-effective, corrosion-resistant, American-made electrical conduit solution for more than 30 years. Learn how to beat inflation ...