For NDOT, one of the biggest challenges was maintaining the flow of traffic for 300,000 vehicles a day on a tight project footprint. “We heavily incentivized the contractor at various milestones throughout the project to get completed to minimize the amount of impact it had to the traveling public,” Mortensen said. In particular, orchestrating the demolition and construction of bridges along the corridor while keeping traffic moving proved to be an arduous task. “I think that anytime you have a project that’s right in the middle of an interstate system like that, access for construction is critical—especially when you’re moving over 1 million cu yd worth of fill.”
In order to enhance safety and highway operations, the Project Neon team implemented ramp braiding along the project in order to avoid the vehicle interaction and competition that occurs when vehicles entering the freeway from an on-ramp try to merge with traffic attempting to exit the highway onto another ramp. “We’re braiding the ramps so the off-ramp would either go over or under the on-ramp traffic,” Mortensen said. “The other thing that’s really helpful for us is the HOV lanes and actually having that direct connect ramp from U.S. 95 to I-15 because that keeps all the traffic and the HOV lanes from having to weave across general-purpose lanes to utilize that ramp movement.”
NDOT is also implementing a new active traffic management (ATM) system—the first of its kind in Nevada—along Project Neon in order to enhance efficiency and reduce travel delays. Forty-two ATM signs will be installed along the corridor in order to help the department actively manage speed and provide information to motorists along a stretch of highway that is expected to double in traffic count over the next two decades.
The team adopted a design-build approach that delivered the project nearly a year earlier than originally anticipated. In addition, contractor Kiewit Construction also beat its own project timeline, partially due to incentives to finish early. “Not only were they done a year faster than we thought anybody could get it done, but they beat their [own] schedule by three months,” Mortensen said.
Work on Project Neon made it to substantial completion by May 15, 2019, with an official ribbon-cutting ceremony that took place in August of this year.
Project: Project Neon
Location: Las Vegas, Nevada
Owners: Nevada DOT
Designer: Atkins North America
Contractors: Kiewit Infrastructure West Co.
Cost: $1 billion
Length: 3.7 miles
Completion Date: August 2019 (ribbon cutting)
About The Author: Bruns is associate editor of Roads & Bridges.