NO. 9 BRIDGE: Brent Spence Bridge Fire & Rehabilitation

Team finishes emergency repairs on fire-damaged bridge in just 41 days

(This feature published as "Springing into Action" in November/December 2021 issue)

December 02, 2021 / 1 minute read
NO. 9 BRIDGE: Brent Spence Bridge Fire & Rehabilitation

The Brent Spence Bridge is a double-decker, cantilevered truss that carries Interstates 71 and 75 across the Ohio River.

In the early morning of Nov. 11, 2020, a truck accident occurred on the northbound lower deck, and fire erupted and caused damage to the bridge’s upper deck floor system steel, drainage, deck, barriers, and electrical components and the lower deck’s overlay, barriers, and electrical components.

After an emergency inspection was performed, the team helped return the bridge to service by providing engineering services, inspection, and fast-paced design to deliver the contract package for repairs within five days.

Facing an emergency interruption to traffic for hundreds of thousands of travelers each day posed a monumental challenge. Immediately following the incident, a “war room” was set up to coordinate pre-construction work encompassing five major work areas: MOT, inspection, design, public awareness, and construction procurement.

Michael Baker quickly decided that the most efficient way to repair the bridge would be to replace damaged components in-kind whenever possible. This allowed the team to use existing design plan sheets/shop drawings for much of the design. Repairs included replacing upper concrete deck, wearing surface, and concrete barriers; replacing upper steel stringers and lateral bracing; replacing miscellaneous steel at upper finger joint; removing, cleaning, and resetting upper finger joint and drainage scuppers; replacing upper deck electrical wiring, junction boxes, and conduit; replacing lower deck wearing surface; replacing lower deck concrete barriers; and replacing fixtures, electrical wiring, junction boxes, and conduit between lower and upper decks.

The bridge reopened just 41 days after the initial incident—under budget and ahead of schedule. After the bridge opened, a documentary was assembled about the entire process.

Project: Brent Spence Bridge Fire & Rehabilitation

Location: Covington, Kentucky

Owners: Kentucky Transportation Cabinet

Designer: Michael Baker International

Contractor: Kokosing Construction Company

Cost: $3.2 million

Length: 1,736 ft

Completion Date: Dec. 22, 2020

About the Author

Related Articles

The Arlington Memorial Bridge Rehabilitation in Washington, D.C. won the Rehabilitated Bridge category at the 2022 PCI Design Awards.
The Arlington Memorial Bridge Rehabilitation in Washington, D.C. won the Rehabilitated Bridge category at the 2022 PCI Design Awards. Image credit: FHWA
The Precast/Prestressed Concrete Institute (PCI) this week have announced some of the winning projects of the 2022 PCI Design Awards. The PCI Design…
January 20, 2022
The Maine Department of Transportation (MaineDOT) recently released the 2022 edition of its three-year work plan. The work plan includes all capital…
January 19, 2022
The U.S. Department of Transportation today launched the Bridge Replacement, Rehabilitation, Preservation, Protection, and Construction Program, made…
January 14, 2022
Sixth Street Viaduct Bridge in Los Angeles reaches engineering milestone
Image: COWI
The engineering team for the new Sixth Street Viaduct in Los Angeles celebrated a project milestone following the successful hanger installation of…
January 07, 2022
expand_less