NO. 8: Maysville Bypass

Nov. 3, 2020

Maysville is a modest-sized community in Jones County, North Carolina.

There a 16-mile piece of roadwork weathered a series of tough challenges to arrive ahead of schedule and on time for this year’s R&B Top 10 Roads.

Of the 4.79 million cu yd of earthmoving on this project, 4.3 million had to be obtained from off-site sources. Fortunately, the JV was prepared. The team set priorities on which properties would take precedence in permitting, in all procuring materials from 10 different locations.

Another challenge was a designed off-site detour that would shut a road down for six months and put school bus traffic down a flood-prone dirt road. NCDOT and the JV formed a DB agreement for the team to design and construct an on-site detour that maintained the original schedule and minimized impacts to the ROW and the environment.

Finally, and certainly biggest, Hurricane Florence devastated Onslow, Jones, and Craven counties. If you witnessed national news of this event, you likely saw footage of these counties as they were the worst hit areas in North Carolina. The teams’ laydown yard was underneath 15 ft of water, an issue that set the team back five months and required nearly $1 million in repairs. 

However, thorough plans were put together in conjunction with NCDOT, and a calculated approach to rebuilding the project ensued. With an acceleration process already put into place, the project was remarkably still able to open to traffic over seven months ahead of schedule.

Of the manner in which crews addressed and bested these challenges, Peter Distefano, Project Manager for Balfour Beatty US Civils, said: “This project was truly a team effort bringing together the expertise of NCDOT and our JV to tackle complex issues quickly, including recovery from damages caused by one of the most devastating hurricanes ever to hit the state of North Carolina. The team overcame this along with a multitude of other issues to open the 16-mile-long highway nearly eight months ahead of schedule and under budget.” 

Project: Maysville Bypass

Location: Maysville, North Carolina

Owner: North Carolina DOT

Designer: North Carolina DOT

Contractors: Balfour Beatty / Branch Civil JV

Cost: $143 million

Length: 16.04 miles

Completion Date: February 2, 2020

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.