NO. 2 BRIDGE: Big Lift, indeed

The rehabilitation of the Angus L. Macdonald Bridge keeps the city of Halifax connected

Brian W. Budzynski / November 01, 2017
Angus L. Macdonald

For Halifax, Nova Scotia, the Angus L. Macdonald Bridge has been an iconic structure for more than 60 years. Years that, as the bridge spans an occasionally rough and always popular Atlantic waterway (Halifax Harbour), had taken a significant toll. As noted in our May 2017 issue (“A new life for the ‘Old Bridge’”), when it came time to rehabilitate the bridge, project planners had a few options to consider, ranging from simple resurfacing to a full-scale conversion to a cable-stay bridge; ultimately, however, mere resurfacing did not address the more critical failure issues at stake, and conversion, aside from presenting too large a risk, would have knocked the bridge out of service for periods deemed unacceptable. The bridge handles approximately 20% of peak capacity traffic flow between Halifax and Dartmouth, some 45,000 vehicles per day.

Project manager Jon Eppell said in May, “Everything goes to gridlock if the Macdonald is taken out of service, so we knew we could not take the bridge out of service . . . or we would cripple traffic flow in the city.

“At the beginning of the ‘Big Lift’ project,” Eppell said, “we had three traffic lanes and two stiffening trusses, which are built-up steel members, not enclosed members, by which I mean we’re not dealing with I-beams, but with angles and plates assembled to create box shapes, but they’re open. Which means there’s been a lot of maintenance on them. The stiffening trusses are above deck, and on the outside of that is the sidewalk and bikeway. The original deck of the bridge was still in place from its original construction for about 25 ft of the deck width. It is a 3-in. steel grid deck with concrete in-fill. Water and salt had dripped over the edge for years, and we had corrosion of the top flange of the supporting beams, which were covered by the deck, so we had no way of accessing them to repair them. That was the trigger for doing this project in the first place. If we left it long enough, it would become a safety issue.”

A specialized gantry system made it possible to install pre-fabricated units 20 m long and about 120 tons each. Crews removed an entire deck piece, lowered it to a barge in the Harbour and brought up a prefabricated piece, then temporarily connected it to the existing deck and permanently to the new deck piece that was installed before it, unit by unit. The units were fabricated with the stiffening truss below the deck, not above it. As a result, they are protected from water and salt off the bridge deck.

Since May, crews set expansion joints on existing approaches and finished paving.

Eppell said, “Now we’re finishing the main cable dehumidification wrapping. We’ve made great strides. We’ll be testing very soon, and hopefully get it commissioned in December.”

Project: Angus L. Macdonald Bridge

Location: Halifax, Nova Scotia

Owner: Halifax Harbour Bridges

Designers: Cowi North American and Harbourside Engineering

Contractor: American Bridge Canada

Cost: $205 million CAN

Length: 1,346.6 m with 762 m suspended span

Completion Date: November 2017

About the Author

Budzynski is managing editor of Roads & Bridges.

Related Articles

NO. 1 BRIDGE: Bayonne Bridge
The Bayonne Bridge project provided nearly 1,500 jobs annually throughout construction, an estimated $380 million in wages and $1.6 billion in economic impact for the region.
Everybody loves a big-ticket bridge build. Even folks who have no real appreciation for structural engineering or the complex geometry at play in the…
November 05, 2019
NO. 2 BRIDGE: Marc Basnight Bridge (Herbert C. Bonner Bridge replacement)
One challenging aspect of the project was working in a sensitive marine environment. The project footprint is home to 20 protected species; the north end of the bridge lands in the Cape Hatteras National Seashore, while the south end lands in the Pea Island National Wildlife Refuge. Several innovative solutions were employed to ensure environmental impacts were minimized.
From the time the Herbert C. Bonner Bridge was built in 1963 over the Oregon Inlet along the North Carolina coast, the structure was in trouble.…
November 05, 2019
NO. 3 BRIDGE: 41st Street Pedestrian Bridge
The city of Chicago has seen a boom of dynamic architectural development in the last 15 years, and the new 41st Street Bridge, which was designed by architects at Cordogan, Clark & Associates, serves as yet another jewel in the Windy City crown.
Through an international design competition called “Bridging the Drive,” the City of Chicago constructed a new signature pedestrian bridge at 41st…
November 05, 2019
NO. 4 BRIDGE: Lesner Bridge
The city had decided early on that they wanted a segmental bridge in order to have longer spans, more curves on the structure, and an aesthetic quality that would fit the bridge into the landscape. One of the factors that was considered in the design phase of the project was to create more space between the pier columns in order to provide unobstructed views of the Chesapeake Bay and Lynnhaven River.
Anyone traversing the area of the Lynnhaven Inlet along Virginia’s southern coast at nighttime would be remiss if they failed to notice the dazzling…
November 05, 2019
expand_less