NO. 2 BRIDGE: Big Lift, indeed

The rehabilitation of the Angus L. Macdonald Bridge keeps the city of Halifax connected

Brian W. Budzynski / November 01, 2017
Angus L. Macdonald

For Halifax, Nova Scotia, the Angus L. Macdonald Bridge has been an iconic structure for more than 60 years. Years that, as the bridge spans an occasionally rough and always popular Atlantic waterway (Halifax Harbour), had taken a significant toll. As noted in our May 2017 issue (“A new life for the ‘Old Bridge’”), when it came time to rehabilitate the bridge, project planners had a few options to consider, ranging from simple resurfacing to a full-scale conversion to a cable-stay bridge; ultimately, however, mere resurfacing did not address the more critical failure issues at stake, and conversion, aside from presenting too large a risk, would have knocked the bridge out of service for periods deemed unacceptable. The bridge handles approximately 20% of peak capacity traffic flow between Halifax and Dartmouth, some 45,000 vehicles per day.

Project manager Jon Eppell said in May, “Everything goes to gridlock if the Macdonald is taken out of service, so we knew we could not take the bridge out of service . . . or we would cripple traffic flow in the city.

“At the beginning of the ‘Big Lift’ project,” Eppell said, “we had three traffic lanes and two stiffening trusses, which are built-up steel members, not enclosed members, by which I mean we’re not dealing with I-beams, but with angles and plates assembled to create box shapes, but they’re open. Which means there’s been a lot of maintenance on them. The stiffening trusses are above deck, and on the outside of that is the sidewalk and bikeway. The original deck of the bridge was still in place from its original construction for about 25 ft of the deck width. It is a 3-in. steel grid deck with concrete in-fill. Water and salt had dripped over the edge for years, and we had corrosion of the top flange of the supporting beams, which were covered by the deck, so we had no way of accessing them to repair them. That was the trigger for doing this project in the first place. If we left it long enough, it would become a safety issue.”

A specialized gantry system made it possible to install pre-fabricated units 20 m long and about 120 tons each. Crews removed an entire deck piece, lowered it to a barge in the Harbour and brought up a prefabricated piece, then temporarily connected it to the existing deck and permanently to the new deck piece that was installed before it, unit by unit. The units were fabricated with the stiffening truss below the deck, not above it. As a result, they are protected from water and salt off the bridge deck.

Since May, crews set expansion joints on existing approaches and finished paving.

Eppell said, “Now we’re finishing the main cable dehumidification wrapping. We’ve made great strides. We’ll be testing very soon, and hopefully get it commissioned in December.”

Project: Angus L. Macdonald Bridge

Location: Halifax, Nova Scotia

Owner: Halifax Harbour Bridges

Designers: Cowi North American and Harbourside Engineering

Contractor: American Bridge Canada

Cost: $205 million CAN

Length: 1,346.6 m with 762 m suspended span

Completion Date: November 2017

About the Author

Budzynski is managing editor of Roads & Bridges.

Related Articles

Skyward’s airspace intelligence
Before a pilot can operate a drone in the field, they need to make sure their operations will be safe. Skyward’s airspace intelligence gives pilots more situational awareness than they would otherwise have, helping reduce risk and minimize unforeseen snags while in the field.
There’s no way around it—infrastructure inspection is as risky and dangerous as it is vital. According to OSHA, sending workers up towers or on top…
September 16, 2019
Crews working off a 3D BrIM model; image courtesy of Zenith Survey
Crews working off a 3D BrIM model; image courtesy of Zenith Survey
Government agencies are under pressure to optimize limited resources while also responding to increasing demands for better performance. Across the…
September 12, 2019
Contractor uses robots to speed up Utah’s largest hydrodemolition bridge repair
Crews direct Aqua Cutters to remove 4 in. of the 8-in. bridge deck concrete with 20,000 psi water jets, leaving 1 in. between the remaining concrete and the rebar. All images courtesy Redi Services unless otherwise noted
Infrastructure repair is a hot topic today, and rightfully so. From potholes to deteriorating bridges, keeping up with repairs—and finding the money…
September 04, 2019
The state of Georgia has had its fair share of major highway projects over the last few years, and it is not about to slow down any time soon. Back…
August 01, 2019
expand_less