MBTA Green Line Extension project over halfway complete

Project will extend the Green Line approximately 4.7 miles north

October 08, 2020
GLX Project Manager John Dalton shows Transportation Secretary and CEO Stephanie Pollack and Governor Charlie Baker GLX construction progress.
GLX Project Manager John Dalton shows Transportation Secretary and CEO Stephanie Pollack and Governor Charlie Baker GLX construction progress. Image: MBTA

State officials recently joined the Massachusetts Bay Transportation Authority (MBTA) General Manager Steve Poftak and project staff to tour the ongoing work with the Green Line Extension (GLX) project.

In conjunction with the MBTA’s $8 billion Building a Better T program, GLX will extend the Green Line approximately 4.7 miles north along two branches from a relocated Lechmere Station to Union Square in Somerville and College Avenue in Medford.

To date, the project is over 50% complete and progressing as scheduled. When complete, GLX will provide service in areas that did not previously have access to reliable public transit, and will significantly reduce vehicle emissions on the road by supporting anticipated increased ridership.

“With construction of the Green Line Extension more than 50 percent complete, we’re well on our way to delivering new rail service to transit-dependent communities in Somerville, Medford, and Cambridge, and providing access to more economic, educational, and recreation opportunities,” Poftak said in a statement.

The total project cost is nearly $2.3 billion, which includes other project components such as real estate, professional services, contingency, and the procurement of 24 new trolleys to augment the existing Green Line fleet. Construction is staffed daily with approximately 650 management and field staff personnel with over 2.5 million design and construction job hours expended as of August 2020. Nearly 77,000 sq ft of retaining walls have been installed within the project corridor, 39,000 cubic yards of concrete have been installed, the installation of caissons supporting the viaduct is 100% complete, and the installation of viaduct steel is nearly complete at 95%. The complete reconstruction of two bridges at Broadway and Washington Streets has been finished with these bridges reopened.

When complete, GLX will have installed 100,000 railroad ties, 21,000 linear ft (nearly 4 miles) of pilings, 22 million lb of steel girders, 17 miles of permanent track, and 2 miles of multiuse community path.

---------

SOURCE: Massachusetts Bay Transportation Authority

Related Articles

This month has been rather eventful in terms of the potential impacts to the intelligent transportation systems, traffic management, traffic safety,…
November 24, 2020
A majority of American voters across the political spectrum support emergency funding for public transportation so that front line workers can get to…
November 23, 2020
Transurban highlights benefits of 395 Express Lanes one year after opening
Image: Transurban
The 395 Express Lanes, opened in November of 2019, are the latest in a series of critical infrastructure projects delivered through a partnership…
November 19, 2020
Biden-Harris administration
Image: Biden-Harris Transition
The transition team of the incoming Biden-Harris administration has laid out plans to invest in "a modern, sustainable infrastructure" as part of the…
November 18, 2020
expand_less