MBTA Green Line Extension project over halfway complete

Project will extend the Green Line approximately 4.7 miles north

October 08, 2020
GLX Project Manager John Dalton shows Transportation Secretary and CEO Stephanie Pollack and Governor Charlie Baker GLX construction progress.
GLX Project Manager John Dalton shows Transportation Secretary and CEO Stephanie Pollack and Governor Charlie Baker GLX construction progress. Image: MBTA

State officials recently joined the Massachusetts Bay Transportation Authority (MBTA) General Manager Steve Poftak and project staff to tour the ongoing work with the Green Line Extension (GLX) project.

In conjunction with the MBTA’s $8 billion Building a Better T program, GLX will extend the Green Line approximately 4.7 miles north along two branches from a relocated Lechmere Station to Union Square in Somerville and College Avenue in Medford.

To date, the project is over 50% complete and progressing as scheduled. When complete, GLX will provide service in areas that did not previously have access to reliable public transit, and will significantly reduce vehicle emissions on the road by supporting anticipated increased ridership.

“With construction of the Green Line Extension more than 50 percent complete, we’re well on our way to delivering new rail service to transit-dependent communities in Somerville, Medford, and Cambridge, and providing access to more economic, educational, and recreation opportunities,” Poftak said in a statement.

The total project cost is nearly $2.3 billion, which includes other project components such as real estate, professional services, contingency, and the procurement of 24 new trolleys to augment the existing Green Line fleet. Construction is staffed daily with approximately 650 management and field staff personnel with over 2.5 million design and construction job hours expended as of August 2020. Nearly 77,000 sq ft of retaining walls have been installed within the project corridor, 39,000 cubic yards of concrete have been installed, the installation of caissons supporting the viaduct is 100% complete, and the installation of viaduct steel is nearly complete at 95%. The complete reconstruction of two bridges at Broadway and Washington Streets has been finished with these bridges reopened.

When complete, GLX will have installed 100,000 railroad ties, 21,000 linear ft (nearly 4 miles) of pilings, 22 million lb of steel girders, 17 miles of permanent track, and 2 miles of multiuse community path.

---------

SOURCE: Massachusetts Bay Transportation Authority

Related Articles

MAX Red Line Extension project in Portland, Oregon
Image: TriMet
The Federal Transit Administration (FTA) recently announced a construction grant award of $99.9 million to the Tri-County Metropolitan Transportation…
September 27, 2021
Every $1 increase in federal highway, bridge, and public transit investment under the Infrastructure Investment & Jobs Act (IIJA) will generate…
September 22, 2021
The U.S. National Science Foundation has awarded the Metropolitan Atlanta Rapid Transit Authority (MARTA) and Georgia Tech Research Cooperation a $1 …
September 21, 2021
The Federal Transit Administration (FTA) today announced the availability of up to $409.6 million in competitive grant funds for building and…
September 20, 2021
expand_less