A recent ruling from a federal judge allowed transportation officials to proceed with a $1.1 billion project to replace the 122-year-old Norwalk River Railroad Bridge—also known as the Walk Bridge—in Connecticut.

The existing movable railroad bridge carries four tracks that serve around 200 trains on a daily basis, which includes Amtrak. The Walk Bridge swings open to allow larger boats coming in from Long Island Sound to pass through.

According to a report from the Associated Press (AP), U.S. District Court Judge Stefan Underhill ruled against opponents of the plan, who filed a lawsuit arguing the current plan is too costly and advocated for cheaper solutions to repairing or replacing the span.

The plaintiffs—which included conservation group Norwalk Harbor Keeper—suggested replacing the current bridge with a fixed span or welding the current bridge shut. These alternatives, they said, would save millions in taxpayer dollars and would cause less disruption to the environment.

A spokesperson for the Connecticut DOT told AP that a number of alternatives were considered for the project, and that the department is continuing to respond to stakeholder and community concerns. Judge Underhill seemed to agree, as his ruling found the involved government agencies on the project properly decided on the approach to this project after considering other options.

The U.S. DOT has said that the $1.1 billion price tag for the Walk Bridge includes engineering, rights of way, and construction costs. This includes a new four-track interlocking system that would allow trains to switch tracks, improvements to another nearby rail line, and other related railroad and bridge work.

---------

SOURCE: Associated Press

Related Articles

In Foxboro, Massachusetts, crews completed a Low-P application over one weekend, avoiding disruption to weekday traffic.
In Foxboro, Massachusetts, crews completed a Low-P application over one weekend, avoiding disruption to weekday traffic.
Sponsored
Concrete is a primary construction material for hundreds of thousands of bridges and bridge decks throughout the U.S. As state DOTs look to preserve…
April 03, 2020
MnDOT announces state road and bridge construction projects lined up for 2020
Image: @MnDOT via Twitter
The Minnesota DOT (MnDOT) announced yesterday that the agency will undertake 188 road and bridge projects statewide during the 2020 season to help…
April 03, 2020
The American Road & Transportation Builders Association (ARTBA) and its partners in the Construction Industry Safety Coalition (CISC) have…
April 02, 2020
Just a few days after signing a $2 trillion relief package to address the economic impacts as a result of the ongoing coronavirus (COVID-19) pandemic…
April 01, 2020
expand_less