ROAD TUNNELS: WSDOT starts on access pit to repair S.R. 99 TBM

May 9, 2014

Environmental review of Seattle Tunnel Partners’ (STP) plan for accessing and repairing the S.R. 99 tunnel boring machine (TBM) is now complete. The on-schedule completion of the review clears the way for STP to build the 120-ft-deep pit that will allow crews to access the machine, which is located about 60 ft below the surface in a fenced-off construction zone between South Jackson and South Main streets.

 

Environmental review of Seattle Tunnel Partners’ (STP) plan for accessing and repairing the S.R. 99 tunnel boring machine (TBM) is now complete. The on-schedule completion of the review clears the way for STP to build the 120-ft-deep pit that will allow crews to access the machine, which is located about 60 ft below the surface in a fenced-off construction zone between South Jackson and South Main streets.

The ground above the machine has been closed for construction since 2012 by the Washington State Department of Transportation (WSDOT), but further environmental review was required for this additional work.

Pit construction will be hard to see in person because crews recently built a wall to shield neighbors from construction noise. The best spot to view STP’s work is online at WSDOT's newly installed time-lapse camera (http://www.wsdot.wa.gov/projects/viaduct/Traffic/ConstructionCam).

The camera went live on Saturday, May 3. On May 7, following completion of the environmental review, STP began assembling equipment where the pit will soon take shape. This work is consistent with the schedule STP released last month. Crews are relocating utilities and will spend the next week injecting grout into the ground above the machine. Later this month, they will begin installing the pit’s underground walls.

STP’s schedule shows that excavation of the pit will last from late July through September. When the pit is complete, the machine will tunnel into it. Crews will then partially disassemble the machine and make repairs. These conceptual drawings illustrate the basic idea (http://www.wsdot.wa.gov/Projects/Viaduct/Media/Default/Documents/Blog/STP_Preliminary_Repair_Plan-1.pdf).

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...