TUNNELS: Seattle’s S.R. 99 project could be delayed for months

Feb. 11, 2014

The S.R. 99 tunnel project in Seattle could be delayed for months following the latest setback with the boring machine, Big Bertha.

 

Bertha has been stalled since Jan. 29, and the prime contractor, Seattle Tunnel Partners, is now considering digging a hole up to 115 ft deep in front of the equipment to make the necessary repairs. Once that task is complete the cutting head for the tunnel-boring machine will be removed by crane.

 

The S.R. 99 tunnel project in Seattle could be delayed for months following the latest setback with the boring machine, Big Bertha.

Bertha has been stalled since Jan. 29, and the prime contractor, Seattle Tunnel Partners, is now considering digging a hole up to 115 ft deep in front of the equipment to make the necessary repairs. Once that task is complete the cutting head for the tunnel-boring machine will be removed by crane.

Chris Dixon of Seattle Tunnel Partners said they were looking at four or five options, but the Washington State Department of Transportation released a statement projecting repairs could take months to make. The project is already four months behind schedule.

“What we’re talking about is, they’re going to excavate the shaft, drive 60 or 70 piles, then lift up the cutterhead,” Lee Newgent, executive secretary of the Seattle Building & Construction Trades Council, said. “They’re looking at least six or seven months.”

Whatever the chosen method, deep piles or walls will have to be used to keep the soft soil and groundwater from affecting the work area.

Following a Dec. 7 shutdown it was discovered that Big Bertha suffered damage to its seals which lubricate the $5 million main bearing. Officials believe the main bearing is OK, but will not know for sure until the manufacturer, Hitachi Nosen, visits the site on Feb. 12.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...