State Route 99 tunnel crews had a busy holiday season working to identify the obstruction that halted the tunneling machine on Dec. 6.
Seattle Tunnel Partners (STP), the Washington State Department of Transportation’s (WSDOT) design-build contractor for the project, spent much of December reducing water pressure in the ground around the machine to make it safe for crews to inspect its excavation chamber. They also drilled 17 exploratory probes in front of the machine to look for objects that might be blocking the machine’s path.
On Jan. 2, contractor crews successfully reduced water pressure enough to visually inspect a portion of the excavation chamber. A piece of an 8-in.-diam. steel pipe could be seen protruding through an opening in the machine’s cutter head. Probes from the surface also detected metal in front of the machine.
The steel pipe is a well casing installed in 2002 following the 2001 Nisqually earthquake to help geologists better understand how groundwater moves in the area. The location of this pipe was included in reference materials in the contract.
“This is just the first step in determining what’s obstructing the machine,” said Matt Preedy, Alaskan Way Viaduct Replacement Program deputy administrator. “We need to investigate further to see if there are other factors that could have contributed to the blockage.”
STP is considering several options to remove the steel pipe and identify other potential obstructions.
“It’s still too early to know how this issue will affect the project’s schedule and budget,” Preedy said. “Our focus right now is on resuming tunneling as quickly and safely as possible.”
As the process to find the blockage continues, workers are conducting critical maintenance, inspecting and replacing damaged cutter tools on the face of the machine.
For more information about the SR 99 Tunnel Project, part of the Alaskan Way Viaduct Replacement Program, visit www.alaskanwayviaduct.org.