Gannett Fleming supports PennDOT S.R. 30 landslide recovery efforts

PennDOT called on Gannett Fleming to provide expertise and assistance on the emergency project

June 26, 2018
S.R. 30 Pennsylvania recovery

On April 7, a significant landslide resulted in the closure of Pennsylvania S.R. 30 in Allegheny County. The route is a principal artery to Pittsburgh and supports more than 22,000 vehicles per day. The slide demolished one apartment building, severely damaged another, and impacted a single-family home.

The Pennsylvania Department of Transportation (PennDOT) called on Gannett Fleming, as a proven partner on similar emergency projects, to provide expertise and assistance. This included performing a visual reconnaissance of the site, executing a cursory review of the available record drawings, and slide remediation advisement for the continued sinking condition of the roadway. Gannett Fleming also consulted with PennDOT on installing bypass pumps of storm drains around the site to limit water infiltration.

“Fortunately, after some initial evaluation of accelerating slope movements, PennDOT and Gannett Fleming decided to close the roadway and evacuate residents at the toe of the slope, including those who lived in the apartment building,” said Brian Heinzl, P.E., Gannett Fleming geotechnical project manager, in a release. “This collaboration was a monumental feat that demonstrates Gannett Fleming’s commitment to the safety of our communities and maintains our position as trusted partners to our clients.”

Under Heinzl’s leadership, Gannett Fleming prepared a comprehensive landslide remediation design and prepared a bid package in just eight working days, which included:

  • Design-build roadway plans for roadway surface and drainage repairs;
  • Details for excavation and benching to remove the landslide material and replace it with durable rock embankment;
  • Final structure plans for construction of a 400-ft-long anchored soldier pile and lagging retaining wall to support the new embankment; and
  • Special provisions needed for PennDOT to advertise the project for bid.

Contractors had four days to review the drawings and prepare a bid. The accepted bid was approximately $6.5 million, only 1% more than Gannett Fleming’s estimate.

The recovery project schedule requires 24/7 operations to remove 35,000 cu yd of material, construct the anchored wall, and rebuild the 90-ft-high slope with engineered fill materials. The goal is to reopen the road by the end of June.

---------

Source: Gannett Fleming

Related Articles

It is estimated that Caltrans saved taxpayers more than $30 million by using a life-extending surface treatment.
It is estimated that Caltrans saved taxpayers more than $30 million by using a life-extending surface treatment.
Every year millions of people travel the iconic Highway 1, also known as the Pacific Coast Highway, stretching along the western coastline of…
March 02, 2020
Madawaska-Edmundston International Bridge
Madawaska-Edmundston International Bridge. Image: Maine DOT
The Maine DOT recently released the 2020 edition of its Three-Year Work Plan, which includes all transportation capital projects and programs, …
January 17, 2020
Nebraska DOT 2020 program book
Image: Nebraska DOT
The Nebraska DOT (NDOT) recently released its 2020 construction program, which details transportation projects scheduled for funding over the next…
September 16, 2019
Maryland DOT Secretary Rahn at launch of Opportunity MDOT
Maryland DOT Secretary Rahn at launch of Opportunity MDOT
The Maryland DOT (MDOT) recently launched Opportunity MDOT, an innovative initiative that connects small, disadvantaged and minority-, women- and…
September 12, 2019
expand_less