CONTRACTOR'S CHOICE GOLD: Texas two-step

July 6, 2012

Ed Bell Construction of Dallas is nearing completion on two years of work along Farm-to-Market Road 1938 in Tarrant County. The project has two parts to it: One involves widening existing portions of FM 1938, also known as Davis Boulevard and Randoll Mill Avenue, to provide more lanes to accommodate increasing traffic.


In addition, crews are building a connecting portion between Randoll Mill and Precinct Line Road. This would extend FM 1938 from I-820 in North Richland Hills to Highway 114 in Westlake, a total of approximately 15 miles.

Ed Bell Construction of Dallas is nearing completion on two years of work along Farm-to-Market Road 1938 in Tarrant County. The project has two parts to it: One involves widening existing portions of FM 1938, also known as Davis Boulevard and Randoll Mill Avenue, to provide more lanes to accommodate increasing traffic.


In addition, crews are building a connecting portion between Randoll Mill and Precinct Line Road. This would extend FM 1938 from I-820 in North Richland Hills to Highway 114 in Westlake, a total of approximately 15 miles.


Initial construction began in June 2010, starting at Highway 114 on the northern end of FM 1938. When building the new portions, crews were able to work on the northbound and southbound lanes simultaneously. As they worked their way south, they could only widen one side at a time in order to keep traffic flowing.


When it came time for structural work, such as putting in retaining walls, the contractor turned to the Caterpillar 320D L hydraulic excavator. Smaller than many of its counterparts, the 320 was perfectly suited for making the shallower cuts of 15 ft or less, according to Ken Brookshire, excavation superintendent and equipment manager for Ed Bell Construction.


The smaller excavator also was useful for laying reinforced concrete pipe for new storm sewer lines, according to Brookshire.


While excavating the footings for the retaining walls, crews hit several pockets of both sugar sand and groundwater, creating muddy conditions that could have been a real setback. Brookshire reported, though, that the 320 performed admirably, allowing them to push through and complete the work with minimal delays.


Brookshire also pointed to the wide availability of replacement parts as another reason Caterpillar was chosen for the job. “Some of the other brands we’ve used in the past, we’ve had to overnight parts or it takes two weeks to get here,” he said. “With Caterpillar, worst-case scenario, we wait overnight for a part through UPS or FedEx.”


In the end, it all comes down to dependability, said Brookshire. “We’ve bought other brands in the past that are good machines for a couple of years, but we’ve got a couple of Caterpillar excavators in our house right now that are over 10 years old and they’re still running.”


Brookshire expected the entire project to be completed sometime in July. R&B

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...