The Design Process
Because CCP innovation is mainly a construction method, the design process saw very little change. The project’s overall scope involved full-depth reconstruction of the two-lane roadway, with rollover curbs to match existing curbs and minimize driveway replacements. Pavement thickness of 8 in. was chosen as the ideal depth for durability, density, and constructability.
Sidewalk on each side of the roadway was also replaced with a wider, ADA-compliant sidewalk. This was designed around utility poles located directly on the back of curb in order to stay within existing right-of-way constraints as much as possible. Permitting, stakeholder engagement, and utility coordination proceeded as usual on the project, with close collaboration and frequent communication to expedite processes as much as possible.
During construction, subgrade soil conditions were discovered to be in poor condition, with a CBR of one and extremely saturated by periodic heavy rains during construction. Design and construction teams considered responding to the challenge with a deep undercut and aggregate stabilization, but that was considered cost-prohibitive and impractical considering the presence of subsurface utilities. The teams moved forward with a 10-in. cement stabilization, which proved the most feasible and efficient option for improving the subgrade.
Innovative Funding
While time was of the essence, so was funding. The city identified the Accelerated Innovation Deployment (AID) Demonstration program as a possible source of funding. Bartlett & West followed up with preparing and coordinating an application through the Missouri Highway and Transportation Department. The AID program, led by the Federal Highway Administration, provides funding as an incentive to accelerate the implementation and adoption of innovation in highway transportation.
Fortunately, the innovative nature of CCP made the Holt Street project a strong candidate for AID funding. The application was successful for this FHWA grant, administered by the Missouri Department of Transportation. In fact, the AID grant covered 80% of the $836,000 reconstruction project.
“To meet the grant criteria, we used compacted concrete paving, hosted a meeting on the day of paving for industry partners to observe and learn, and we also prepared a final report for FHWA to recap lessons learned from this innovative project,” said Steve Schultz, P.E., the Bartlett & West engineer who helped the city secure the grant.
The CCP Difference
The use of CCP allowed for all paving operations to occur in a single day. Furthermore, cure time was minimized due to the innovative material meeting a required compressive strength sooner than traditional materials would have. In fact, field data showed that Holt Street could have reopened within 24 hours of construction. However, because an adequate traffic management plan was in place, alleviating some of the schedule pressures, the project team chose a more conservative approach with a seven-day cure time. This allowed the pavement to achieve 4,600 psi before reopening.
The relatively dry mix allowed the project to achieve a rapid early strength, thereby limiting the downtime of grain trucks accessing the ADM facility. Unique characteristics that made CCP more desirable than traditional concrete pavement included no reinforcement, no formwork, and the laying method resembling that of asphalt.
“Data shows we saved at least a half-day of production time by using compacted concrete paving, and preserved emergency access for our residents.” Russell said. “There is no doubt the CCP method made a difference on this short—but very important—corridor for the city of Mexico.”
About The Author: Kempker is senior project manager with Bartlett & West.