Crane, bulldozer partner to set cantilever bridge in North Carolina

Feb. 13, 2019

Cranes and bulldozers rule different realms: one, the air and the other, land. So it is not every day they collaborate on setting a bridge, but they did just that for a temporary cantilever bridge in Aurora, N.C., in January. The 125-ft span is needed to maintain traffic flow on Rte. 33 over Campbell Creek while the North Carolina Department of Transportation (NCDOT) replaces the permanent bridge.

ALL Carolina Crane Rental of Wilmington, a member of the ALL Family of Companies, provided a Link-Belt ATC-3210 for setting the temporary bridge. The bridge itself was prefabricated and shipped to the site, then assembled on land near one of the creek banks.

ALL Crane positioned the ATC-3210 on the resting side of the bridge, on the opposite bank, and hooked up to it. The 210-USt crane was configured with 124 ft of boom and a full counterweight of 115,500 lb. Outriggers were extended for additional support, and the radius ranged from 95 ft to 45 ft.

To prepare for its placement, the bridge was set on a special roller system. The bulldozer, from general contractor Dellinger Inc., began to slowly push the bridge toward the crane. ALL Crane’s operator and the bulldozer operator were in constant radio communication to assure an even transfer. In addition, another ALL Crane crew member was positioned on the old bridge, acting as a spotter.

“Our operator had to methodically boom up while keeping the hoist line even, so it was vital that he and the bulldozer operator would act as one,” said Scott Harbaugh, sales representative for ALL Carolina Crane Rental of Wilmington. “We had to prevent any shock weight to the crane, so we needed a smooth, even transfer.”

At the load’s heaviest point, the ATC-3210 was at 45 ft of radius and was supporting 66,000 lb. “We were at zero weight until the bridge reached the tipping point,” said Harbaugh. “Then with each 5-ft push, the crane would take on a little more weight until we had the full 66,000 lb. It required skilled operators and steady hands on both sides of the bridge.”

The bridge was set on a new concrete slab, and a ground crew came in to lay asphalt and finish it off. The temporary bridge will remain in place until the new permanent structure is completed. “At that time, we’ll be back out here and basically do it all over again in reverse,” said Harbaugh. “We’ll pick it up with the crane and they’ll pull as we boom out.”

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...