No. 2 BRIDGE: King of the mountain

Nov. 12, 2013

Who would have thought the Missing Link would be found in Tennessee?


The Missing Link, in this case, is a 1.6-mile portion of the Foothills Parkway in Great Smoky Mountains National Park. Commissioned by Congress in 1944 as a 72-mile scenic route, the Foothills Parkway remains unfinished today, with only 22.6 miles completed. It is the oldest unfinished highway project in the state of Tennessee.

Who would have thought the Missing Link would be found in Tennessee?


The Missing Link, in this case, is a 1.6-mile portion of the Foothills Parkway in Great Smoky Mountains National Park. Commissioned by Congress in 1944 as a 72-mile scenic route, the Foothills Parkway remains unfinished today, with only 22.6 miles completed. It is the oldest unfinished highway project in the state of Tennessee.


More specifically, the Missing Link is in Section 8E, a 9.7-mile portion of the Foothills Parkway that is nearly complete. Ten bridges make up the Missing Link. Bridge No. 2 is the largest span in the section, with a series of reverse curves that cut through some of the steepest terrain—vertical grades range from 6.75% to 8.02%.


The site itself was far and away the biggest challenge on the project, according to Hratch Pakhchanian of the Eastern Federal Lands Highway Division (EFLHD). As a result of the steep grade on the site, workers had to be extremely careful where and how they cut.


“Any disturbance of the ground could cause instability,” Pakhchanian told Roads & Bridges. “The slightest cut could take out a whole side of the mountain.”


Geography and environmental concerns restricted the available working space on the jobsite as well. A previous environmental assessment confined the scope of work to the limits of the bridge itself, which is only 37 ft wide. Topping off the laundry list of difficulties, workers only had access from the eastern approach.


Faced with these challenging conditions, the project team decided to precast Bridge No. 2. (The other bridges in the Missing Link have all been cast-in-place.) The superstructure is made of 92 segments, each one unique due to the geometry of the site.  


To facilitate construction on such a difficult jobsite, EFLHD constructed falsework and a specialized gantry crane, dubbed the Segment Walker. Crews bored holes for micropiles for the falsework foundations. Once established, the crane traveler attached directly to the falsework and progressed forward throughout construction, lowering the precast pier and superstructure segments into place. “We could not have built this bridge without it,” Pakhchanian said.


The new bridge has an expected design life of 100 years. As of press time, construction was continuing concurrently on bridges 3 through 7. EFLHD and the National Park Service are currently on target to open the Missing Link to traffic in 2016. R&B

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...