Storm-water treatment does not effect tight working windows on I-64/I-255 interchange in East St. Louis

June 7, 2013

In most ways, the resurfacing of the I-64/I-255 interchange near East St. Louis, Ill., was an ordinary—albeit big—project; it’s a large cloverleaf intersection and extremely busy, but paving contractors Keeley & Sons Inc. are used to that. However, there was one unique feature; “Most years, we install maybe 10-15 catch-basin risers—for the whole year,” explained Project Engineer Bob Germann. “But on this project alone, we installed a total of 100 catch-basin risers.”

 

In most ways, the resurfacing of the I-64/I-255 interchange near East St. Louis, Ill., was an ordinary—albeit big—project; it’s a large cloverleaf intersection and extremely busy, but paving contractors Keeley & Sons Inc. are used to that. However, there was one unique feature; “Most years, we install maybe 10-15 catch-basin risers—for the whole year,” explained Project Engineer Bob Germann. “But on this project alone, we installed a total of 100 catch-basin risers.”

The catch basins lined a barrier wall that separated access ramps from main lanes, which meant that crews working on the basins would be exposed to traffic. This could have been a problem; as part of the contract, lane closures had to be kept to a minimum. “That’s pretty common around here.” said Germann, “On this project, we couldn’t close lanes at all during peak hours, from 6-9 a.m. westbound and 3-6 p.m. eastbound.”

Keeley use catch-basin risers and manhole risers from American Highway Products. The manhole risers were previously approved for use by the Illinois Department of Transportation, and the department approved the use of the catch-basin risers for the I-64 project.

“I’m really glad we had the risers available,” says Germann. “Without them, we would have been forced to hammer out the existing frames and pour new concrete; it could have taken a couple of weeks just on that part of the job.”

The catch-basin risers used on the job are custom-made for particular projects, and can be easily installed with hand tools—the entire process takes just a few minutes per riser. Keeley & Sons’ crews installed the risers after the binder course was laid, and before the final paving lift. Instead of a couple of weeks, all 100 catch basins were raised to grade in just two days.

Every project has its wrinkles and surprises. By looking for a better method, Keeley & Sons were able to smooth out a major obstacle and prevented a “catch” from turning into a big problem.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.