The U.S. 50 project was complicated by the corridor’s function as a major trucking bypass to I-70. Consequently, traffic control was a daily issue during active reclamation and paving, as shown here.
Crazy couldn’t be more right
Virgin materials were used when this stretch of U.S. 50, a two-lane road with 10-ft shoulders, was resurfaced 15 years ago, so when cores were evaluated leading up to the CIR project it was determined that the existing pavement was an ideal candidate for recycling.
“CIR is quite a crazy product compared to hot in-place, but [CIR] was very effective because the material was so good along that stretch,” said Gray. “We made all of our numbers based off of the test, so we were good to go.”
A Roadtec milling machine came in and took off 4 in. of existing pavement. It took a total of four passes to cover both lanes and shoulders. However, there was a section of roadway where there were 40-ft-wide lanes and 10-ft shoulders, which meant 4 ft had to be reprocessed and remilled. The CIR remixing machine picked up the windrowed asphalt and mixed 1¼-in. aggregate with 1.5% hydrated lime and 2% recycled oil, but with the wider passing lanes the blending was getting a bit misconstrued.
“We found out the lime was 30% higher because of the reprocessing,” said Gray. “So based on that we were like, ‘Whoa, [the contractor] blew the lime’ because we had a unit cost to that one. They blew the lime by $75,000 because [the contractor] had to reprocess the wider lanes through 40 ft.”
The recycled layer was used for the base course, which varied in depth from 5 to 9 in. Areas that required thicker sections were due to past landslides, and CDOT maintenance crews came in and added more material. Bomag vibratory rollers came in and handled compaction in just three passes, and some of the densities were over 100%.
“It is that good of material when it comes out of the machine, the lime heats it up and anytime you have heat you are able to get it down tighter,” commented Gray.
Next came the 2-in.-thick surface mix, which was produced from a Gencor asphalt plant about 10 miles from the work site. A PG 75 SX asphalt binder was used, aggregate size was 1.5 in., and temperature at laydown was 275-300°F. A Roadtec paver handled laydown duties, and a Bomag vibratory roller and Caterpillar and Hamm pneumatic tire rollers worked together to hit a 94% density in just five passes. A quarter-mile test section that used fiberglass in the asphalt mix also was put down. A Troxler nuclear gauge was used to check for density, and A & S Construction had an experienced construction worker taking random reads; if he found a spot that was unacceptable he would put a pin in the pavement.
“It was test here, test there, test here,” explained Gray. “He had 30 years of experience, and I really think having someone out there with experience helped. He gets paid [based on] how well the pavement is.”
The contractor also made sure the center joint in the pavement was treated properly. A special wheel roller welded to the paver compacting at an angle did the trick. A profilograph and 10-ft-long level was used to check for smoothness. Five spots had to be regrinded, but the contractor did receive $126,000 in smoothness bonus.
U.S. 50 lies in one of the most environmentally sensitive areas in the state, and special precautions were taken to protect the threatened Gunnison Sage Grouse breeding grounds along the corridor. Paving hours were limited to 10 a.m. to 4 p.m. Staging of the CIR lime and recycled oil also was a critical issue because no spills were allowed due to the reservoir and endangered habitats.
“It was a huge topic here,” said Gray. “We worked with the Division of Wildlife and they were happy with what we did. I never saw a Gunnison Sage Grouse . . . I was happy we obeyed the time restrictions.”
About The Author: Wilson is editorial director of Roads & Bridges.