2011 Top 10 Bridges - No. 9

Nov. 30, 2011
I-270 OVER DORSETT ROAD
PROJECT: I-270 Over Dorsett Road
LOCATION: Maryland Heights, Mo.
COST: $10 million
LENGTH: 2,232 ft
DESIGNER: HDR Inc.
CONTRACTOR: Fred Weber Inc.
OWNER: Missouri DOT
They were counting the days in Maryland Heights, Mo. Using the diverging diamond interchange con?guration, a ?rst in the St. Louis region, crews constructed two bridges, one at a time, in just 56 days on Missouri’s busiest section of highway. During construction of bridge one, there was just 4 ft of space between the bridge to be demolished and the adjacent temporary bridge.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.