VDOT officials underestimate Mixing Bowl price

Dec. 3, 2002
Big projects continue to grow out of control in the U

Big projects continue to grow out of control in the U.S. According to an audit issued by the U.S. Department of Transportation's inspector general, Virginia's "Mixing Bowl" road project is reaching a $1 billion price tag. Back in 1994, the state's Commonwealth Transportation Board chose a $241 million design for the Springfield Interchange.

Big projects continue to grow out of control in the U

Big projects continue to grow out of control in the U.S. According to an audit issued by the U.S. Department of Transportation's inspector general, Virginia's "Mixing Bowl" road project is reaching a $1 billion price tag. Back in 1994, the state's Commonwealth Transportation Board chose a $241 million design for the Springfield Interchange. Today the job is now up to $676 million and the cost continues to rise. The pattern reflects the one taking by Boston's "Big Dig", which received national ridicule for overspending.

The audit listed four key changes behind the fiscal adjustment:

* VDOT added more ramps from the interchange to Franconia and Old Keene Mill roads. The project grew to include the widening of Loisdale Road and Commerce Street (added cost: $30 million);

* Public demands for more noise walls were heeded, and bridge engineers believed could be redecked were replaced. More retaining walls were built to allow extra work on utilities (added cost: $54.3 million);

* When widening Franconia Road required taking land from Lee High School, the Fairfax County School Board demanded compensation (added cost: $500,000); and

* Fairfax County supervisors demanded broader efforts to ease congestion during construction. VDOT answered the call by increasing state police presence, expanding local bus service and improving roads in the area. The state also financed an information center in Springfield Mall.

A number of omissions were made when the $241 million estimate was figured back in 1994, with the largest being the rate of inflation. From 1994 to 2001, VDOT did not assume any increase in the cost of materials or labor for the life of the project. In 2001, at the urging of federal auditors, the department began assuming a modest 3% increase in prices each year. The added cost for this mistake is $44 million.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.