TOP 10 ROADS: Getting it done––early

Oct. 6, 2011

The I-385 rehabilitation in Laurens, S.C., was a 14.6-mile road construction project that had to be completed in only eight months because of road-closing constraints—a tight deadline, made tighter because of challenges like weather delays and unexpected terrain conditions. Despite this, the project actually finished 24 days early.

Preparation, especially development of a rigid schedule, was key in shaving time off the project completion, Nick Wolf of McCarthy Improvement Co., the contractor, told ROADS & BRIDGES.

The I-385 rehabilitation in Laurens, S.C., was a 14.6-mile road construction project that had to be completed in only eight months because of road-closing constraints—a tight deadline, made tighter because of challenges like weather delays and unexpected terrain conditions. Despite this, the project actually finished 24 days early.

Preparation, especially development of a rigid schedule, was key in shaving time off the project completion, Nick Wolf of McCarthy Improvement Co., the contractor, told ROADS & BRIDGES.

“We went through about 200-300 iterations of the initial schedule,” Wolf said.

McCarthy also conducted extensive interviews with subcontractors and chose those who were willing to commit to multiple crews working multiple shifts, Wolf said.

“The key factor was being able to work on every available portion of the project on any given day and to not have a portion of the project that wasn’t touched when it was available,” he said.

Despite diligent planning, the weather cannot be controlled. During January to July 2010 construction, the crews dealt with three snowstorms and 110 rain days, including two 25-year rain events.

“This really put a strain on all the earthwork and other weather-dependent items,” Wolf said. “We had to increase the work force. We went from two crews to seven crews near the end.”

Another unforeseen issue was the terrain. Wolf said after they cleared the heavily wooded area along the roadway, the majority of the roadway was a straight drop-off from the edge of the shoulder down to the slopes, making it unsafe for drivers.

“We weren’t expecting the condition of the existing slopes,” he said. “We ended up having to do a whole rebuild of the slopes over the whole 15 miles of the project.”

The preparation and extra effort paid off in the end when the project finished early, Wolf said.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.