Printer-friendly versionSend to friend
Tuesday, April 24, 2001 - 23:00
Self-performed Dewatering Enhances California Sewer Line Project

The trunkline connects a pump station in the municipality’s sanitary sewer system with a large wastewater treatment plant operated by the Monterey Regional Water Pollution Control Agency.

The Yuba City, Calif. grading, paving and underground contractor gained several benefits from using its own workforce to dewater the work zone. The labor and equipment costs to self-perform the requirement ran about the same as to subcontract the work. The investment in pumps, well sleeves, discharge line and generators has equipped Jaeger to self-perform the work again on future projects.

"The most important thing for me was the increased control we gained over the job," emphasized Mike Robertson, Jaeger Construction’s veteran project superintendent.

"We’re always better off doing as much work as possible with our own forces. It turned out successful enough that I can foresee us doing it again and again."

The project replaced a 48-in., unlined reinforced concrete (RC) line that had been in service for 35 years with more acid-resistant HDPE line and components. Included were 9,000 feet of 54-in. segmental pipe; 4,000 ft. of miscellaneous runs; 30 molded manholes ranging size from 48 in. up to 120 in. and two 10-ft. diameter inverted siphon structures. The alignment runs 50 ft. from and parallel with the original 4,000,000 GPM line that had experienced repeated structural collapses caused by the crown being eaten away by sewer gases. Plans called for plugging the old line after completion of the larger replacement.

Sandis Humber Jones served as the project’s design engineers, with the Salinas Public Works Department providing inspection. The $4.2-million contract was awarded in July, 2000 with an anticipated 100 working days scheduled for a crew consisting of five equipment operators and five laborers. Equipment included a CAT 330, two CAT 235 units, an Hitachi 750, a Komatsu 1100, CAT D-8 dozer and two CAT 950 loaders. Jaeger Construction was exceeding the anticipated 100 feet per day when rains swept the area around Christmas and cost the project two weeks. The majority of the work has involved cut-and-fill trenching to depths ranging from 15 to 35 feet below grade. Exceptions were several hundred feet of 6-ft. diameter bores dug under four roadways and a railroad crossing. The only other known hurdle to overcome in planning the project was the relatively high watertable along the path of the line. Chris Jaeger, and Hans Norlander, a sales representative for ITT Flygt, collaborated in planning and identifying the equipment needed to lower the watertable long enough in work areas to dig the trench and install the segments of new line. After analyzing the watertable and site conditions along the line, they concluded that one hundred Model BS2052 Flygt submersible pumps would be ideal for the task. The 1.6-HP, 460 volt/3-phase units would be powered by four generators.

The Flygt pumps are rated at 120 GPM and with a maximum 60-ft. head and feature a durable design features that makes them resistant to failure even when running dry for extended periods of time. Reliability, in fact, was a decisive factor in their selection and can be attributed to an impeller molded from hardened cast iron alloy and wear parts protected with a polyurethane liner. With several options available, Jaeger Construction settled on 3 phase, 460-volt service to gain longer cable runs off the 70 KW generator units. The pumps were wired in 24-unit groups, with three pumps linked to a common junction box. Portable control was retained for each pump to protect against motor short circuits or overloads. The light weight of the 711Ú16-in. diameter pumps — just 40 pounds — would also make them easy to remove and relocate to new wells ahead of the work crew.

It took the field crew six weeks to drill the initial 100 wells that established the first area dewatered. The wells were generally placed at 80-ft. to 100-ft. spacings with the grid extended 35 feet out from the center of the trenchline at points requiring a wider, safer trench line. Each well was lined with 10 feet of interlocked sections of 10-in. diameter, Schedule 40 PVC pipe. The lower 20 feet of these well liners were perforated to allow the water to flow freely into the pipe. A plastic bucket at the bottom of each well prevented large solids from clogging the sleeve.

The pumps typically would run around the clock for a minimum of three weeks before the crew could work the drained area. Twenty-five wells would be ganged into an 8-in. line that discharged into the storm drainage system. At least 48 pumps would operate while 24 others in trailing areas were pulled and advanced to wells drilled downline. The abandoned wells were then filled with pea gravel. The remaining pumps were held in reserve to contend with areas having higher than expected water levels or as replacements.

After observing dewatering contractors perform the work for many years, Robertson was fully confident that Jaeger Construction could perform the work. He eagerly took on the added task.

"I didn’t find the dewatering all that challenging and wouldn’t hesitate to do it again," Robertson said, adding, "The equipment is a lot more advanced than when I started in construction.

"But those were the days when we used smoke signals to communicate instead of cell phones," he joked.

For further information, phone 203-380-4700.

Roads&Bridges Videos

 

Industry News

A piece of federal legislation in the works is making Chicago transit directors very nervous, according to the Chicago Tribune.   The...
The two-year transportation bill pushed by the Senate could be one step closer to a Congressional showdown if it receives enough votes necessary for...
Federal Highway Administrator Victor Mendez yesterday reviewed preparations for the construction of the new Memorial Bridge connecting Portsmouth, N....

Products

  • Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
  • The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
  • The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
  • Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
  • Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
  • Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
  • Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
  • BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
  • American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
  • The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...