Polymer Concrete Wearing Surface System for Orthotropic Steel Deck Bridge

The Poplar Street bridge across the Mississippi River in St. Louis, Missouri is an orthotropic steel-plate deck bridge. It carries three major interstate highways, I-70, I-64 and I-55 across the Mississippi River at St. Louis, Missouri. Approximately 130,000 vehicles including about 15,000 large trucks use the bridge each day. The five-span bridge is 2,165 ft. long and consists of two independent bridges supported on a set of common piers. Each bridge carries four lanes of traffic and is supported by two box girder with girder depths ranging from 16 ft. to 25 ft. The deck plate thickness is typically 9/16 in. and is stiffened by closed trapezoidal stringers or ribs. The 5/16 in. thick stiffeners on 13 in. centers are 11 in. deep and run along the length of the bridge. Load from the deck is also transferred to the box girders by transverse floor beams coinciding with every fourth floor beam location, providing the bridge additional torsional rigidity. There are approximately thirty such orthotropic steel-plate bridges in the world including six in the United States.
When the bridge was constructed in 1967, the steel deck was covered with a wearing surface consisting of two layers of epoxy tack coat and 1 _ inches of rubberized asphalt concrete wearing surface. Stone chips were embedded in the second layer of epoxy as an anchor for the rubberized asphalt layer. This wearing surface system performed well until 1983. When the first wearing surface was no longer serviceable it was removed completely to expose bare metal of the deck and a replacement wearing surface was applied. This second wearing surface was intended to be identical to the original surface. The second wearing surface lasted less than three years. The eastbound lanes were replaced for a third time in 1986. This third wearing surface incorporated a proprietary system that included a fiberglass reinforcing mat in the asphalt wearing surface layer. Despite the reinforcing mat, unacceptable amounts of rutting and shoving necessitated the placement of a new wearing surface during the 1992 construction season.
Six wearing surface material systems were evaluated as potential replacements for the wearing surface on the Poplar Street Bridge by researchers and the University of Missouri-Columbia (MU) under a Missouri Highway and Transportation Department (MHTD) contract. Two were asphaltic concretes, three were epoxy polymer concrete and one was a methyl methacrylate polymer concrete. Laboratory tests included flexural fatigue tests on wearing surface-deck plate composite specimens at a constant temperature of 0°F, flexural fatigue tests under cyclic temperature variations from 0°F to 160°F, and ancillary tests (resistivity and pull-out tests) to evaluate the condition of the surfaces before and after the fatigue tests. Concurrently with the laboratory tests, a test section of each material was placed on the bridge by its supplier and subjected to normal traffic up to 2 years. These field test sections were observed regularly for evidence of rutting, shoving, cracking, delamination or other signs of deterioration. Based on the performance of these materials in the laboratory tests and the test sections on the bridge Transpo T-48 polymer concrete was observed to be the best of the materials tested and the only material that did not delaminate or fail during the field test period.
The MHTD selected and exclusively specified Transpo T-48 polymer concrete for the new wearing surface. Placement of this wearing surface was started in July 1992 and completed in August 1992.
A total of 20 working days was used by the contractor, Pace Construction, Co. of St. Louis, Missouri, to place the 226,000 sq. ft. of _ in. thick overlay. Transpo Industries worked with Eltech, Inc. to design a specialized and highly accurate self contained mobile mixer for the large volume mixing of the Transpo T-48 slurry. Transpo Industries of New Rochelle, New York supplied all of the materials for the Transpo T-48 Polymer Concrete Overlay System.
No prior field experience was available on the use of polymer concrete wearing surface systems on large steel decks subjected to a combination of severe environmental and heavy traffic conditions. Also since there was potential for cracking and delamination, particularly at the colder temperatures, and conventional crack maintenance programs were considered unlikely to work for the new material, the MHTD was interested in closely monitoring the long-term performance of the new wearing surface system. MU was awarded a five-year contract for long-term inspection and testing of the wearing surface. The yearly inspection includes resistivity tests to qualitatively monitor cracking in the wearing surface, pull-out tests to establish the adhesion strength in tension between the wearing surface from the deck-plate, observations to record wearing surface thickness, aggregate loss and other signs of deterioration.
Two visible cracks, one at each end of the southmost-lane (in the transition zone from 2 _ in. thick at the finger joint to _ in. thickness of the overlay on the eastbound bridge) which appeared after one year of service were repaired using neat Transpo T-48 epoxy polymer. No further crack growth or deterioration of the wearing surface in the vicinity of the cracks were observed even after two years since the repair. While the cause for these cracks has not been conclusively established, differential thermal expansion significant to the only lane with the cracks whose beam was exposed to sunlight is being studied as a possible culprit.
After being in service for approximately three years, the Transpo T-48 polymer concrete wearing surface system has been performing very well. There have been no additional cracks. Neither has there been any delaminations, loss of skid resistance, excessive wear or any failure to date.

Roads&Bridges Videos

 

Industry News

By a vote of 17-7 and one present vote, the Senate Finance Committee on Feb. 7 approved a list of revenue enhancers to provide the $5.5 billion...
Foes of the planned San Antonio streetcar system said last Tuesday that county officials broke a promise with voters when they agreed to use advanced...
A 322-ft span of the U.S. 68/Kentucky 80 bridge over Kentucky Lake in far western Kentucky collapsed after being struck by a barge Jan. 26....

Products

  • Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
  • The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
  • The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
  • Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
  • Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
  • Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
  • Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
  • BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
  • American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
  • The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...