Printer-friendly versionSend to friend
Wednesday, March 21, 2007 - 09:15
Over Done

Long ago, there was no requirement to have a differing site condition or significant change in the character of the work clause in the state standard specifications.
As some contractors know, Congress left a loophole under which states could “opt out” of having the clauses, and some states have done so.
Even in states that have the differing site conditions clause and change in the character of the work clause in their contracts, it is not unusual for the state DOT to deny claims for quantity overruns. The argument typically is that the quantities are just estimates used to compare bids, and that such claims are barred by the clause that requires contractors during the bid period to “thoroughly examine the site.” Some state courts simplistically buy those arguments, but not the Virginia Supreme Court. Contractors take heart; there is hope in these cases.

Overruns aren’t overruns
In June 1992, Asphalt Roads and Materials Co. Inc. contracted with the Virginia Department of Transportation (VDOT) to widen a section of road. Asphalt Roads subcontracted the installation of the utility pipes. That work required removal and replacement of any unsuitable soil under the utility pipes, with an estimated quantity of 940 cu yd. During excavation, the subcontractor had to remove and replace substantially more than 940 cu yd of unsuitable soil.
Asphalt Roads, on behalf of its subcontractor, claimed additional compensation for the excess unsuitable material that was discovered, removed and replaced with borrow. VDOT paid for the removal of some of the material as an “unforeseen condition” covered by Section 104.02 of the Standard Specifications. VDOT also paid for some of the backfill under Section 303.06(d). VDOT declined to pay the balance of the claim.
Asphalt Roads filed suit. The trial court held that the contractor was entitled to payment for an additional 8,657 cu yd of backfill and 8,807 cu yd of unsuitable material at the contract-stated unit price of $6.18 for select borrow.
The case eventually ended up at the Virginia Supreme Court. In deciding the case, the Virginia Supreme Court had to determine whether the contractor was entitled to additional compensation for removing and disposing of the excess unsuitable material under the differing site conditions clause or at the contract unit price. Citing cases from other states, the court first considered the purpose of the differing site conditions clause “to encourage low, competent bids,” and “to take at least some of the gamble on subsurface conditions out of bidding.” The court noted there will be no windfalls or disasters and that the state benefits from bids without contingencies.
VDOT argued that the differing site conditions clause did not apply to quantity overruns. The court disagreed by finding that treating the quantity overruns as nothing more than quantity overruns would defeat the purpose of the differing site conditions clause.
VDOT also argued that the claim should be denied based on the site investigation clause in the Standard Specifications. The court rejected that position, stating, “If we applied these sections to the change of condition shown in the evidence in this case, we would render meaningless the language of sections like 104.03 and negate their salutary purposes.”
This Virginia Supreme Court decision is well reasoned and it is consistent with the realities of bidding and construction. In the short time available for bidding, a contractor does not have time to find the design errors or determine that the quantities are out of whack. The DOTs do get the benefit of lower bids, and in return should compensate contractors when the quantity overruns change the character of the work.

Roads&Bridges Videos

 

Industry News

The Ohio Department of Transportation (ODOT) is hoping to generate millions of dollars in new money by launching a program that will permit...
As the people in and around Atlanta prepare to decide on a sales-tax referendum that could generate $6.14 billion for transportation upgrades,...
Utah’s S.R. 92 project should have been completed in late 2011, but traffic cones are still visible. Now the state legislature is telling the Utah...

Products

9733 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...