Monday, November 30, 2009 - 09:54
NCDOT caught in another paving mistake

Counties will be forced to pay for crumbling I-795

The North Carolina Department of Transportation covered for its own mistake, but it will end up costing six counties about $12 million.
A mix design error and other lapses at the NCDOT resulted in 18 miles of bad pavement being laid on I-795. In late November crews started to mill 1.5 in. of the crumbling road and will add another 3 in. of new asphalt in an effort to strengthen the pavement.
The agency was under the direction of Lyndo Tippett when the botched project was executed, and it marked the second time the NCDOT came under fire for poor road construction during Tippett’s tenure. During the first, NCDOT admitted to making a costly paving blunder on I-40 in Durham County. Tippett’s highway administrator resigned and several others were disciplined as a result, and state legislators agreed that Durham and other counties should not be held responsible for the repair. They also demanded reform.
The state, however, is not offering the same kind of assistance for the I-795 debacle, even though highway officials issued warnings about the pavement thickness. Jim Trogdon, the NCDOT’s chief operating officer who was the No. 2 administrator under Transportation Secretary Gene Conti when I-795 was in its design phase, tried to get another 3 in. of asphalt applied, which would have added $2 million to the $196 million project.

The News & Observer

Roads&Bridges Videos

 

Products

  • Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
  • The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
  • The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
  • Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
  • Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
  • Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
  • Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
  • BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
  • American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
  • The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...