Printer-friendly versionSend to friend
Tuesday, July 15, 2008 - 11:49
Mashing units

Most highway contracts include Variation in Estimated Quantity (VEQ) clauses that establish rules governing the renegotiation of unit prices if actual quantities vary from the government’s estimated quantities by a stated percentage—typically between 15 and 25%. Many VEQ clauses distinguish between minor and major bid items and allow adjustments for the former, but not the latter. Alternatively, a minor bid item might require a substantially greater variance in quantity than a major bid item before the unit price may be negotiated. In nearly all instances, a request for an increase or decrease in a unit price under a VEQ clause must be based upon an increase or decrease in costs due solely to the variation in quantity.

Unsuitable maneuver

Contractors and state highway departments sometimes forget that the VEQ clause is not the only contract provision affecting quantity changes, and in some events unit price changes are warranted even when quantity changes are less than the threshold percentages stated in the VEQ clause.

Cases have similarly held that the government cannot apply a VEQ clause to foreclose unit price changes when the additional (or reduced) quantities are attributable to changes in the work. Rather, pricing in such instances is governed by the changes clause contained in the contract. Accordingly, contractors must keep in mind that the VEQ clause is not the sole mechanism in the contract governing whether work must be performed at the contract unit prices bid. Frequently, other contract clauses apply and take precedence over the VEQ clause.

Flashing a message

Once the VEQ clause is deemed properly applicable, the party seeking the unit price adjustment must prove that the contractor’s cost of performing the particular item of work has increased or decreased as a sole result of the variation in quantity. As the Maryland Court of Special Appeals determined in Genstar Stone Paving Products, Co., Inc. v. State Highway Administration, 616 A.2d 256 (1993), this can be shown only by comparing the contractor’s costs of performing the estimated quantity to the contractor’s cost of performing the added quantity. More importantly, how much profit, if any, the contractor is making on the work is irrelevant.

Genstar Paving involved a VEQ clause that allowed unit price adjustments for quantities varying by greater than 25% of the estimate. When the estimated quantity for the variable message board bid item overran from 200 unit/days to 555 unit/days, the department sought a reduction in the unit price of $900, which it argued was $845 higher than the statewide average price bid for variable message boards. In the appeal, the department argued that once the contractor performed the original quantity plus 25%, additional units should be performed at a lower price because the contractor’s actual costs were significantly lower than its $900 bid price.

The court acknowledged that the contractor’s price was over eight times its actual cost. However, it held that the clear and unambiguous language of the VEQ clause restricted the inquiry to whether the contractor experienced a cost reduction as a sole result of the additional quantities. How much the contractor is profiting from the work is not to be considered. The appeals court, therefore, remanded the case to the trial court to make that determination.

What if the contractor had underbid and it sought a price adjustment under these circumstances to offset its losses? The inquiry would be restricted to whether the contractor’s costs for the added quantity increased as a sole result of such added quantity. Absent an increase in costs that could be tied solely to the increase in quantity, no adjustment in price would be allowed.

Roads&Bridges Videos

 

Industry News

The Ohio Department of Transportation (ODOT) is hoping to generate millions of dollars in new money by launching a program that will permit...
As the people in and around Atlanta prepare to decide on a sales-tax referendum that could generate $6.14 billion for transportation upgrades,...
Utah’s S.R. 92 project should have been completed in late 2011, but traffic cones are still visible. Now the state legislature is telling the Utah...

Products

8534 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...