Written Notice

April 1, 2023
Beware that strict compliance of the contract might be required

By Jon Straw

When an owner replaced a contractor for significant safety violations, the owner sought to recover the costs for a replacement from the original contractor. A Texas jury found that the owner and the terminated contractor each breached the contract. Both sides were awarded damages and attorney’s fees.

The jury decided that, although two of the written notices required to recover the replacement costs were technically absent, there was sufficient communication between the owner and terminated contractor. Forcing the terminated contractor to pay the replacement costs was proper and an intermediate appeals court agreed.

The Texas Supreme Court reversed the jury’s and the intermediate appellate court’s holding that strict compliance with notice requirements is generally not necessary, unless such notice requirements are part of a written contract.

In this instance, the failure to comply with the written notice requirements did not invalidate the termination. However, the owner could not recover its replacement costs, which were only recoverable after having provided the required written notices before termination. James Construction Group, LLC v. Westlake Chemical Corp., 650 S.W.3d 392, Supreme Court of Texas (May 20, 2022).

In this case, the contractor was to perform certain civil and mechanical construction work on the owner’s chemical plant located in Geismar, La. The contractor was contractually “responsible for the safety and health of its employees and Subcontractors” and “for the adequacy, stability and safety of all operations, construction [of] temporary facilities, construction equipment and the construction site and methods necessary for the performance of the Work.”

The owner had a contractual right to “intervene” if they reasonably believed that personal injury or property damage may result from the contractor’s performance. The owner could terminate the contract for convenience “at any time.”

The owner could terminate the contractor for default, but only after the owner had provided three separate written notices, plus a single 72-hour cure period. After a proper default termination, the terminated contractor was obligated to pay costs for a replacement contractor.

After several safety incidents including multiple “OSHA-recordable” injuries, “near misses,” and a fatality, the owner terminated the contractor for default (or so the owner thought).

The owner exchanged several internal e-mails about the contractor’s safety record, one of which was also sent as a courtesy (or carbon) copy to the contractor, characterizing a safety incident as “completely preventable. The owner also requested a safety review to show how such incidents would be prevented. This e-mail did not reference the default clause, safety clause, or notice requirements of the contract.

The Texas Supreme Court reversed the jury’s and the intermediate court of appeals’ determination that this e-mail was sufficient written notice before a default termination. The Supreme Court reasoned that adequate notice should “communicate sufficient information to enable [the recipient] to reasonably conclude that [default] was at play and the [cure period] was ticking.”

Expressing concerns about safety, even as important as are such concerns, is not necessarily the notice contractually required to recover damages for replacement costs after a default termination. But even if this e-mail was a sufficient first notice, the contract required two more separately written notices before an effective default termination.

For further reading, the Chief Justice of the Texas Supreme Court authored a dissent disagreeing with the majority opinion. The dissent is at least entertaining, if not interesting. The dissent argues that under the “substantial compliance” doctrine, the language of the owner’s e-mail with the contemporaneous context could be sufficient notice, particularly if there was no harm to the receiving party, and full technical compliance was not necessary, even when a contractual provision so required.

With this opinion, Texas has now joined some other states that have seemingly raised form above function when providing notice. Some state-level public contracts even require mandatory, or so-called “magic,” language for notice to be legally sufficient.

Take notice of both the contract and the status of the applicable law when notifying, even for significant safety violations. R&B

About the Author

76086

Jon Straw is a partner with Kraftson Caudle, PLC, a law firm in McLean, Va., specializing in heavy-highway and transportation construction. Straw can be contacted via e-mail at [email protected].

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.