Because most state highway departments assume the risk of fuel-cost escalation and include price-adjustment clauses in their contracts, contractors generally feel no financial effects by varying fuel prices. These clauses, however, are not always clear, and as a case in Mississippi demonstrates, disputes sometimes arise concerning how adjustments are calculated.
The case involved a contract to construct 6.25 miles of highway for the Mississippi Department of Transportation (MDOT). The contract included a fuel-adjustment clause that established a base fuel price upon which all bidders were to base their bids. Adjustments would be made on each pay estimate based upon variances between the base price and a specified index that MDOT publishes each month. The last sentence of the clause addressed adjustments for work performed after the contract completion date as follows: “After expiration of the contract time, including all extensions, adjustments will be computed using fuel and material prices that are in effect at the expiration of the contract time.”
Once the contractor exceeded the adjusted contract completion date, MDOT began making fuel adjustments in accordance with its interpretation of the provision, which was to essentially freeze the monthly index price in effect as of contract completion date, and all payments thereafter were made based upon the difference between the original baseline price and the “frozen” index price.
The contractor did not object, because for many months thereafter, fuel prices were fairly stable. However, when Katrina struck in August 2005, prices skyrocketed and MDOT continued making adjustments based upon the relatively small variance between the original baseline price and the frozen index price. From this point, the contractor lost nearly $500,000 and, consequently, it filed a claim, which MDOT denied. The contractor sued.
Price check
The contractor argued that the adjustment clause merely requires MDOT to reset the original baseline price to the index price current as of the contract completion date, and each subsequent monthly adjustment should be based upon the difference between the revised baseline and the current index price. It also argued that if the department’s interpretation is a correct one, the clause violates the state statute that grants the department the authority to include fuel-price adjustment clauses in its contracts.
The trial court rejected both arguments, and the contractor appealed to the Supreme Court of Mississippi. Like the trial court, the Mississippi Supreme Court agreed with MDOT’s interpretation. However, it agreed with the contractor’s contention that the clause exceeds the statutory authority granted MDOT to include such clauses in its contracts, and it remanded the case back to the trial court for a full trial.
The court focused on the requirement in the statute that adjustments must be made “with relation to the cost to the contractor” and ruled that by freezing the monthly index for payments after the contract completion date, subsequent adjustments were arbitrary and thus no longer took the contractor’s cost into account.
Although this outcome is a rare one, it highlights the importance of procurement-related statutes in public contracts. Public contracts must always be read in concert with enabling legislation. Certain procurement statutes provide additional terms that are regarded as part of the contract. Other statutes expand on the meaning of written public contract terms. Lastly, and as demonstrated in Mississippi in this case, statutes can actually take precedence over written contract terms and even invalidate them, especially if they are written contrary to a particular statute. Therefore, to fully understand their contracts, the public contractor must familiarize themselves with the procurement statutes in the states in which they work.
More like this
Roads&Bridges Videos
Industry News
Products
2431 Products
-
The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format. The FVT/...
-
RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
-
Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
-
Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
-
JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
-
Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
-
The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
-
Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
-
The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
-
Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...









