Fit to overlap

April 18, 2002

During the summer of 2001, an innovative remedy was applied to a 5.5-mile section of I-40 in eastern Oklahoma. The project specified dowel bar retrofitting and overlaying an existing concrete pavement. The retrofit and overlay were not completed in two separate steps, as is most commonly done. By changing the construction methods and combining the placement of the load transfer devices along with the overlay, the contractor saved significant time and costs. 

Finding faults

During the summer of 2001, an innovative remedy was applied to a 5.5-mile section of I-40 in eastern Oklahoma. The project specified dowel bar retrofitting and overlaying an existing concrete pavement. The retrofit and overlay were not completed in two separate steps, as is most commonly done. By changing the construction methods and combining the placement of the load transfer devices along with the overlay, the contractor saved significant time and costs. 

Finding faults

The project is located in Sequoyah County on I-40, approximately 35 miles from the Arkansas border. The existing pavement consisted of 9 in. of plain jointed concrete over 4 in. of fine aggregate base course placed over 6 in. of fly ash treated subgrade.

Constructed in 1969, the pavement was extensively faulted with some longitudinal cracking and shattered slabs. The designed average daily traffic for the section was 18,200, with 28% trucks.

After a trial section was shown to be constructible and durable, simultaneous dowel bar retrofit and bonded overlay was determined to be a good rehabilitation technique for this section. Despite the faulting, most of the individual slabs were in good condition. Investigation showed that loss of aggregate interlock and stripping of the fine aggregate base was the primary cause of faulting.

The original rehabilitation design called for the surface to be prepared by shot blasting, slot cutting, dowel bar placement and a 4-in. layer of concrete over the entire pavement area. The dowel bars would be 18 in. long and 11/2 in. in diam. Three bars would be placed in each wheel path. Two dowel bar slot options were made available in the original design, and they could  either be placed in individual slots or three dowels per one large slot in each wheel path. Both options are commonplace in dowel bar retrofit jobs.

Before the overlay was placed, longitudinal cracks needed to be secured and some slabs removed and replaced. 

As with any concrete design, cost is an important factor. Method of payment for the paving was by the cu yd of concrete and by the sq yd for placement. Additionally, since pavement edge drop-off would be limited to 4 in., traffic crossovers would not be utilized, resulting in an overall cost savings for the project.

No shot

Preparations were made for the bonded overlay. After approval from the Oklahoma Department of Transportation (ODOT), the contractor, Bryan Adair Construction, Broken Arrow, Okla., used a milling machine in lieu of shot blasting. 

First, the entire surface was roughened by removing the top 1/2 in. to ensure a good bond. This was done using a CMI PR-800-7/12 milling machine (Circle 936) with a 12-ft-wide, 42-in.-diam. barrel grinder. Milled pavement showed a roughened surface that appeared adequate to bond to the overlay. The contractor estimated that milling was up to three times faster than shot blasting. 

After milling, the surface was swept twice using water, then swept an additional two to three times dry. 

During milling, the drum of the milling machine was lowered an extra 4 in. at the existing joint. A 4-in.-deep trench was milled approximately 24 in. wide, enough to accommodate the 18-in. dowel bars and the baskets supporting them. 

Crack repair and slab replacement followed. Steel was placed to tie longitudinal cracks and, similar to large staples, these consisted of epoxy-coated No. 4 rebar. The top is 18 in. long, and the “legs” are 8 in. long. The “staples” were inserted into the existing pavement 61/2 in., with 30-in. spacing. 

Full-depth replacement was required for shattered slabs,  133 panels were fully replaced and 33 panels were partially replaced using high-early-strength concrete. 

Lowering the bars

Baskets holding 11 dowel bars in each lane were placed in the trench and secured to the existing pavement with fasteners. The dowel bars used were 11/4 in. in diam., the standard used in the state for new construction. ODOT allowed this by using a no-cost change order since the overall cross section steel surface area would be greater than the area provided by the six in the original design. 

The contractor noted that construction times for previous jobs which used a slotting machine were slower and had high slotting machine costs. According to the contractor, the increased productivity of using the 11 bars per lane more than offset the cost of the additional bars. 

Paving was performed one lane at a time using a Gomaco CP 2600 standard concrete paver (Circle 937) to apply the 4 in. of fiber-reinforced overlay. Compressed air was used to clean the surface steps ahead of the paver. 

After placement, the overlay surface was transversely tined before applying a white pigment curing compound. 

Daily high temperatures during paving reached 100°F. This required early morning operations and a double application of curing compound. Three “soft cut” saws cut a 4-in.-deep joint within three hours of concrete placement to reduce the risk of excessive cracking. The construction joints were then cleaned and sealed with a self-leveling silicone joint sealant. 

The entire project was completed within the allotted construction time.

Strong and smooth

Coring performed through one of the dowel bars showed effective consolidation on all sides. Iowa shear tests were run on cores without steel, with results ranging from 470 to 557 psi. The minimum acceptable shear strength according to the ACPA Technical Bulletin TB-007 P “Guidelines for Bonded Concrete Overlays” is 200 psi.

Final inspection in January 2002 showed smoothness of less than 4 in. per mile with very few cracks. 

About The Author: Burwell is executive director of the Oklahoma/Arkansas chapter of the American Concrete Pavement Association. Benson is the pavement and materials engineer with the Oklahoma Division of the Federal Highway Administration.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.