If the government wrongfully refuses to grant a time extension for an excusable delay, any claim for delay damages by the government will be unjustified.
More important, if the government either denies a legitimate time request during the project or fails to act in a timely manner upon such a request, it will be deemed to have “constructively” ordered the contractor to accelerate the schedule and thus is responsible for any reasonable costs the contractor incurs attempting to complete the project within the original contract time period.
Five-speed
In a perfect world, a contractor that encounters a delay outside of its control promptly alerts the government to the delay-causing event, and once the extent of the delay can be quantified, the government responds to a formal request for time by either granting all or a portion of the request or denying it altogether. This is perfect because both the government and contractor are placed in a position where they can make intelligent decisions on going forward. The government, presented with a timely request, can consider both the entitlement and quantum of the time request and whether it desires the contractor to accelerate to make up for lost time. The contractor—having received a prompt response to its request—is either relieved from the cloud of delay damages hanging over its head (if the request is granted) or is empowered to decide whether it makes more sense to finish late and face the government’s delay damages or incur additional costs to accelerate the schedule. Regardless of whether the contractor or owner is ultimately responsible for the delay, the contractor’s decision on whether or not to accelerate must be reasonable.
“Constructive acceleration” occurs when the government requires the contractor to meet the original delivery schedule despite the existence of excusable delays. There are five requirements for constructive acceleration: (1) an excusable delay; (2) knowledge by the government of the delay; (3) a statement or act by the government that can be construed as an order to accelerate; (4) notice to the government by the contractor that such statement or act is construed as an acceleration order; and (5) the incurrence by the contractor of acceleration costs.
In practice, constructive acceleration most commonly occurs when the government either wrongfully denies a legitimate time extension request or fails to act in a timely manner on such a request. In order to fully satisfy the five requirements identified above, the contractor must first turn in a substantiated request for a time extension. Then it is not enough that the government either wrongfully denies the request or fails to respond within a reasonable time. The contractor must place the government on notice that its failure to act on the request or its denial of such request is considered by the contractor as an order to accelerate the project. The contractor should also inform the government in writing that it will seek at a later date all costs incurred in connection with acceleration efforts.
Excuse yourself
Until a formal request for a time extension is made, the government has no duty to extend the contract time. More important, any acceleration efforts or re-sequencing of the work by the contractor to mitigate the impact of an excusable delay will not be compensable until the government either (1) expressly orders such mitigation; (2) wrongfully denies a legitimate time request; or (3) fails to act within a reasonable time on such a request. Contractors, therefore, must instill in their project management personnel the importance of quantifying the impact of excusable delays as soon as possible and promptly placing before the government a formal request for extension of time. Similarly, government contract administration personnel must be mindful of the ramifications of their decisions on time extension requests and their failure to provide a timely decision.
Roads&Bridges Videos
Industry News
Products
-
Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
-
The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
-
The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
-
Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
-
Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
-
Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
-
Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
-
BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
-
American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
-
The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...