An Education on Traffic Management

It is estimated that road-user costs on a typical urban highway rehabilitation project can exceed $50,000 or more per day. Since 1973, the number of vehicle miles driven has increased 86% while the number of lane miles built has increased only 33 according to The Road Information Program (TRIP). This increased congestion and the need to upgrade and replace aging pavement has created an overwhelming demand for information on traffic management.
For years, the American Concrete Pavement Association (ACPA) and its contractor members have been committed to “getting in, doing the job right, getting out and staying out.” At the same time, the ACPA has led and supported efforts to minimize road-user delays without trading off performance, quality, safety or any of the other features commonly associated with portland cement concrete (PCC) pavements.
Through a cooperative agreement with the Federal Highway Administration, the ACPA is developing an education program on how to consider road-user impact during the rehabilitation of PCC pavements. The program will provide traffic management options for resurfacing, restoration and reconstruction. The plan involves a traffic management handbook, a series of workshops and a national open house, all scheduled to begin this year.

Traffic management basics
The course is oriented toward DOT officials for both central and district/regional offices, as well as project designers, traffic control plan specialists, contractors, public safety officers and public affairs practitioners.
Traffic management involves the balancing of three competing interests: the traffic and how it is handled through the work zone, the work itself and how it is done, and the public and local businesses and how they are involved in the project.
Each element represents a value for time and cost. If only the construction were important, then the optimal method might be to place detours and remove traffic from the project area. On the other hand, if only the traffic were considered important then the optimal solution may be to defer the work and not to disrupt any traffic. Neither of these extremes are probable for most projects. As such, traffic management seeks to apply principles that allow a balance among the three competing interests.
Each project may involve one or more of a number of traffic handling or control scenarios. Eight standard scenarios are available: lane constriction, lane closure, shared right-of-way, temporary by-pass, intermittent closure, cross-over, shoulder/median use and detour.
Traffic management initiative
The goal of ACPA’s traffic management initiative is to maintain construction quality while optimizing concerns of owners and users. The course’s handbook outlines a five-step process for a balanced strategy. They include: choosing feasible traffic-control scenarios; considering planning issues such as incident management, utility interruptions, emergencies and business access; comparing alternatives; choosing a recommended traffic management strategy; and determining phasing or other constraints and provisions such as public information, public relations and intra-agency coordination.
ACPA’s traffic management initiative ensures that a number of variables are considered to compare and contrast alternatives. These variables include: traffic-control measures, construction requirements, operational performance, constructability, emergency planning and public information and coordination.
The key is managing expectations of the agency, businesses affected by the project, road-users and the public-at-large.

Roads&Bridges Videos

 

Industry News

Foes of the planned San Antonio streetcar system said last Tuesday that county officials broke a promise with voters when they agreed to use advanced...
A 322-ft span of the U.S. 68/Kentucky 80 bridge over Kentucky Lake in far western Kentucky collapsed after being struck by a barge Jan. 26....
The February issue of Roads & Bridges is now available under the Current Issue section of the website.

Products

  • Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
  • The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
  • The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
  • Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
  • Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
  • Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
  • Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
  • BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
  • American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
  • The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...