Ambitious I-65/I-70 project in Indianapolis rolls on

Nov. 3, 2021

The I-65/I-70 North Split Interchange project in Indianapolis continues with an aggressive timeline that calls for the construction of 50 bridges in 18 months. A prominent downtown bridge got the rebuild treatment when the span carrying northbound and southbound lanes of I-65 over Central Avenue was completely replaced.

Central Rent-A-Crane, a member of the ALL Family of Companies, provided cranes for general contractor Superior Construction. The job called for setting precast, prestressed beams which were manufactured by Prestress Services Industries. 

To minimize traffic disruptions, the lifts were scheduled for overnight, creating one of the more challenging scenarios encountered in the crane business: a two-crane night pick.

Each direction of the bridge, southbound and northbound, required six beams for a total of 12. Beams weighed in at 42 tons, measuring 80 ft long. To accommodate the load, Central Rent-A-Crane specified Grove GMK6300L and Grove GMK7550 all-terrain cranes for the dual picks. 

The GMK6300L has a 350-ton capacity and was configured with 120 ft of main boom at a 45-ft radius with 208,000 lb of counterweight. It was chosen because its capacity fell well within the weight and reach requirements. As there was not another 350-ton class AT available, the second crane was a 550-USt GMK7550, configured with 116 ft of main boom also at the 45-ft radius. It required 176,000 lb of counterweight. 

Setting beams for each direction of the bridge took only one night each. “We had a lane closure from 7 p.m. to 5 a.m. for each night,” said Ronnie Baker, sales representative from Central Rent-A-Crane. “That gave us a 10-hour window to pick and set six precast bridge beams.”

Baker says trucks from the manufacturer began lining up along the highway just prior to the 7 p.m. lane closure so the truck carrying the first beam could drive into position immediately. From there it was a continuous process, with each beam taking 30 to 60 minutes to pick and set.

“The orientation of the jobsite allowed the cranes to be far enough away to pick in tandem, cable up, and swing at the same time,” Baker said. Spotters strategically positioned with a complete view of the work zone were in constant radio communication with the crane operators. 

“This went remarkably smoothly,” Baker said. “It’s a credit to the organization of the contractor and the supplier, and the execution of our operators.” Ironworkers returned to the site later to put in deck pans and rebar and pour concrete.

Rigging for the beams was handled by Superior Construction’s crew, with team members able to rig beams in just a few minutes each. Cranes were set up behind concrete barriers, well away from the single lane of traffic that was maintained overnight. 

The North Split project will continue through next year and into 2023. Baker says Central has begun discussion with the project’s contractor about the next bridge to be constructed.

Editor's Note: Scranton Gillette Communications and the SGC Infrastructure Group are not liable for the accuracy, efficacy and validity of the claims made in this piece. The views expressed in this content do not reflect the position of the Roads & Bridges' Editorial Team.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.