Printer-friendly versionSend to friend
Wednesday, November 18, 2009 - 08:27
Card trick

Changes and alterations in the work are a necessary evil in heavy-highway construction work. For this reason, public and private owners expressly reserve the right to make changes in their contracts via changes in the work clauses. A question I am frequently asked is whether an owner’s right to make changes under a changes clause is unlimited. The short answer is no. Unfortunately, the line of demarcation between permissible and impermissible changes is a gray and meandering one.

Backfilling backfiring

Within the federal contracting arena, the Cardinal Change doctrine has developed. The black-letter definition of a Cardinal Change is one that is “outside the scope of the contract.” My favorite Cardinal Change case is Peter Kiewit Sons’ Co. v. Summit Constr. Co., 422 F.2d 242 (8th Cir. 1969), which involved an excavation subcontractor responsible for backfilling 150 underground missile silos constructed by the prime contractor. Knowing that a significant amount of piping would be installed by other subcontractors on the exterior of the silos, the subcontractor negotiated into its subcontract a provision ensuring that it would not be responsible for backfilling or working around the piping. That provision specified that the first stage of backfill would be installed to an elevation immediately above the highest piping and, after other subcontractors installed and backfilled their piping, the subcontractor would finish the remainder of the backfill.

The dispute arose when the prime required the subcontractor to perform the backfill in several stages rather than two and to work around and backfill for piping that was installed by others. Eventually, the subcontractor refused to continue its work, and the prime contractor terminated the subcontract.

In determining whether a Cardinal Change occurred, thereby justifying the subcontractor’s refusal to perform, the court noted that the number of changes alone is not determinative and the point at which a change becomes too substantial “is really a matter of degree.” This “matter of degree” is a judgment that each court must make based upon the facts and circumstances of the case. By virtue of the subjective nature of this inquiry, court decisions are often inconsistent and conflicting.

The Kiewit case represents one end of the spectrum of Cardinal Change decisions. The court determined that the changes went beyond the scope of the subcontract and cited a $1.4 million increase in the subcontractor’s estimated backfill cost of $600,000 as a significant factor in its decision.

Self-help guidance

Although many states do not recognize the Cardinal Change doctrine, the Abandonment of Contract theory is quite similar and is widely recognized. However, these cases similarly involve subjective judgments based upon the facts and circumstances of each case and, therefore, produce widely varying results.

Contractors confronted with significant project changes should consider whether they have a legitimate claim for Cardinal Change or Abandonment of Contract. However, because of the uncertainty and unpredictability inherent in the case law, the self-help remedies of refusing to perform or terminating the contract should be considered only in the most egregious circumstances.

Roads&Bridges Videos

 

Industry News

Utah’s S.R. 92 project should have been completed in late 2011, but traffic cones are still visible. Now the state legislature is telling the Utah...
The latest national traffic signal assessment conducted by the National Transportation Operations Coalition (NTOC), a group of transportation...
The cost of construction materials took a breather in April, while contractors showed slightly greater ability to roll past price increases into...

Products

1337 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...