No. 4 - IH 635/LBJ Managed Lanes

Oct. 7, 2016

Operating on orders to double the capacity for traffic mobility, but design “no higher and no wider,” design firm Bridgefarmer & Associates worked tirelessly over the course of five years to complete the I-635/LBJ Managed Lanes project in Dallas.

A project that had been on TxDOT’s books for nearly three decades, the I-635/LBJ Managed Lanes project reconstructed the freeway’s eight existing general-purpose lanes and added six new managed, depressed lanes in an excavated trench section.

“I-635 was one of the worst-congested freeways in the country for many, many years,” Mansoor Ahsan, P.E., CEO of Bridgefarmer & Associates, told Roads & Bridges. “And TxDOT has tried to widen the corridor many times, and simply couldn’t because it’s fully developed.”

For the 17-mile project, Bridgefarmer proposed the concept of a “no tunnel option” or “open cut” solution for the project. The innovative concept became the solution as a result of the restrictions TxDOT mandated for the project to be built no higher than existing lanes on the interstate and no wider than the existing right-of-way, due to the placement of a plethora of businesses and housing developments along the corridor. In addition, the open cut became a less expensive solution than the originally proposed tunnel option.

What made the open cut practical for the Bridgefarmer team was that it enabled them to simply design one span, and then repeat that design for each section of the project.

“If I am mobilized for one span, I can repeat it a hundred times or a thousand times,” Ahsan said. “Our team did exactly that; we came up with one span, and we repeated it throughout the corridor.”

A significant challenge for the managed lanes project was keeping lanes open throughout construction. “TxDOT required that the existing number of lanes be maintained the majority of the time,” Project Manager Lisa Deitemeyer told Roads & Bridges. “So we had to set our alignments so that we could phase the job in such a way that we could maintain the number of lanes of traffic and build a new corridor of roadways, bridges and walls—that was a big challenge of the job.”

Opening a year earlier than anticipated, toll revenues along the LBJ since completion of the project in September 2015 indicate significant improvements on the corridor, since revenue has been much higher than originally anticipated. Since the freeway moved 270,000 vehicles per day prior to construction, Bridgefarmer & Associates anticipates that the new managed toll lanes will be capable of withstanding 500,000 vehicles by 2020.

Location: Dallas, Texas

Owner: Texas Department of Transportation

Designer: Bridgefarmer & Associates Inc.

Contractor: Trinity Infrastructure LLC

Cost: $2.7 billion

Length: 17 miles

Completion Date: September 2015

Sponsored Recommendations

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...

Transform Your Concrete Highways: The Game-Changer for Long-Lasting PCCP Joint Protection

Concrete highways are a critical piece of infrastructure in the United States, essential for the reliable transportation of people and products. Yet in many cases, their service...