2012 Top 10 Bridges: No. 4 — Feat of concrete

Feb. 21, 2013
Mississippi deltas rise at St. Louis
PROJECT: Mississippi River Bridge
LOCATION: St. Louis
OWNER: Missouri DOT and Illinois DOT
DESIGNER: HNTB Corp.
CONTRACTOR: Joint venture of Massman Construction, Traylor Brothers and Alberici Constructors
COST: $667 million
START DATE: Feb. 15, 2010
COMPLETION DATE: Aug. 20, 2014

One of the most challenging tasks in constructing the new Mississippi River Bridge between St. Louis and southwestern Illinois was casting the massive concrete foundations for the towers.


Each of the two tower footings is 24 ft deep, 55 ft wide and 88 ft long. They are the largest of the mass concrete objects on the project. The tower bases sit on top of the footings and rise 70 ft above to the base of the bridge deck. Each massive foundation contains more than 1.9 million lb of closely packed reinforcing steel. The reinforcing steel was nicknamed the “canary cage” by some workers, who joked that even a canary could not fit between the bars.


Pouring the concrete for the first foundation, on the Illinois side of the river, took 43 hours and involved more than 3,600 cu yd of concrete.


Below the two foundations are six 12-ft-diam. drilled shafts sunk through about 30 ft of water, 70 ft of silt and mud and 20 ft of limestone.


The delta-shaped towers for the new Mississippi River Bridge reached their full 400-ft height over the summer. The bridge as a whole reached No. 4 on the Roads & Bridges Top 10 Bridges list.


The bridge is the first bridge built in more than 40 years between downtown St. Louis and southwestern Illinois. The new bridge will carry the rerouted I-70 across the Mississippi River and give drivers less congestion and less travel delay than they have been experiencing with I-70 sharing the Poplar Street Bridge with I-55, I-64 and U.S. Rte. 40. The cable-stayed main span of the bridge will be 1,500 ft long, with a total span of 2,803 ft.


The deck segments and stay cables will be assembled at the same time in balanced-cantilever method.


Construction of the four-lane deck for the bridge has started and workers are connecting the first of more than 600 miles of cable between the towers and the roadway.

Construction work for the Illinois approach is proceeding well. Crews have completed installation of all the girders on the Illinois approach and have started the initial work to form up the driving surface. The Missouri approach structure is complete.


Live pictures of the construction site are available on the project’s website at www?.newriverbridge.org.


Construction of the bridge is part of the larger project of rerouting I-70, which also involves constructing a roadway connection between the existing I-70 on the Missouri side of the river and the new bridge, a roadway connection between the new bridge and the existing I-55/64/70 Tri-Level Interchange in Illinois and improvements at the I-55/64/70 Tri-Level Interchange. R&B

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.