TUNNEL CONSTRUCTION: WSDOT finds pipe might be blocking S.R. 99 tunnel machine

Jan. 6, 2014

State Route 99 tunnel crews had a busy holiday season working to identify the obstruction that halted the tunneling machine on Dec. 6.

 

Seattle Tunnel Partners (STP), the Washington State Department of Transportation’s (WSDOT) design-build contractor for the project, spent much of December reducing water pressure in the ground around the machine to make it safe for crews to inspect its excavation chamber. They also drilled 17 exploratory probes in front of the machine to look for objects that might be blocking the machine’s path.

 

State Route 99 tunnel crews had a busy holiday season working to identify the obstruction that halted the tunneling machine on Dec. 6.

Seattle Tunnel Partners (STP), the Washington State Department of Transportation’s (WSDOT) design-build contractor for the project, spent much of December reducing water pressure in the ground around the machine to make it safe for crews to inspect its excavation chamber. They also drilled 17 exploratory probes in front of the machine to look for objects that might be blocking the machine’s path.

On Jan. 2, contractor crews successfully reduced water pressure enough to visually inspect a portion of the excavation chamber. A piece of an 8-in.-diam. steel pipe could be seen protruding through an opening in the machine’s cutter head. Probes from the surface also detected metal in front of the machine.

The steel pipe is a well casing installed in 2002 following the 2001 Nisqually earthquake to help geologists better understand how groundwater moves in the area. The location of this pipe was included in reference materials in the contract.

“This is just the first step in determining what’s obstructing the machine,” said Matt Preedy, Alaskan Way Viaduct Replacement Program deputy administrator. “We need to investigate further to see if there are other factors that could have contributed to the blockage.”

STP is considering several options to remove the steel pipe and identify other potential obstructions.

“It’s still too early to know how this issue will affect the project’s schedule and budget,” Preedy said. “Our focus right now is on resuming tunneling as quickly and safely as possible.”

As the process to find the blockage continues, workers are conducting critical maintenance, inspecting and replacing damaged cutter tools on the face of the machine.

For more information about the SR 99 Tunnel Project, part of the Alaskan Way Viaduct Replacement Program, visit www.alaskanwayviaduct.org.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.