TOP 10 ROADS: Getting it done––early

Mary Beth Nevulis, Associate Editor / October 06, 2011

The I-385 rehabilitation in Laurens, S.C., was a 14.6-mile road construction project that had to be completed in only eight months because of road-closing constraints—a tight deadline, made tighter because of challenges like weather delays and unexpected terrain conditions. Despite this, the project actually finished 24 days early.

Preparation, especially development of a rigid schedule, was key in shaving time off the project completion, Nick Wolf of McCarthy Improvement Co., the contractor, told ROADS & BRIDGES.

“We went through about 200-300 iterations of the initial schedule,” Wolf said.

McCarthy also conducted extensive interviews with subcontractors and chose those who were willing to commit to multiple crews working multiple shifts, Wolf said.

“The key factor was being able to work on every available portion of the project on any given day and to not have a portion of the project that wasn’t touched when it was available,” he said.

Despite diligent planning, the weather cannot be controlled. During January to July 2010 construction, the crews dealt with three snowstorms and 110 rain days, including two 25-year rain events.

“This really put a strain on all the earthwork and other weather-dependent items,” Wolf said. “We had to increase the work force. We went from two crews to seven crews near the end.”

Another unforeseen issue was the terrain. Wolf said after they cleared the heavily wooded area along the roadway, the majority of the roadway was a straight drop-off from the edge of the shoulder down to the slopes, making it unsafe for drivers.

“We weren’t expecting the condition of the existing slopes,” he said. “We ended up having to do a whole rebuild of the slopes over the whole 15 miles of the project.”

The preparation and extra effort paid off in the end when the project finished early, Wolf said.

About the Author

Related Articles

Nowhere is the extremity of our national geography more apparent than in the states that draw down from the Canadian border and through what was once…
July 03, 2019
In fall 2018, the Virginia DOT (VDOT) reached substantial completion on the Route 460 Southgate Connector. This project included replacing the…
July 03, 2019
According to the Federal Highway Administration’s (FHWA) Office of Highway Policy Information, nearly 53% of rural highway mileage is under county…
June 24, 2019
Along with being one of the most sizable and significant banking centers in the nation, Alabama’s largest city is also a primary hub for rail…
June 07, 2019
expand_less