Sponsored

Three cranes assist with Pennsylvania’s Southern Beltway Construction

September 09, 2020
Three cranes assist with Pennsylvania’s Southern Beltway Construction

Pennsylvania’s massive new highway construction project rolls on. Dubbed the Southern Beltway, the turnpike extension is the state’s first entirely new highway construction in decades. The latest phase includes construction of new bridges for nearby I-79 because construction crews had to burrow underneath this interstate to create a route for the new Southern Beltway to tunnel through. The existing I-79 remained open, with two-way traffic diverted to either the northbound or southbound lanes while the new bridges were being built. 

Alvarez Inc., which specializes in bridge construction, is using a trio of powerhouse cranes from ALL Crane Rental of Pennsylvania, a member of the ALL Family of Companies, to set bridge components. The three machines have a combined capacity of 1,300 tons: a Liebherr LTM 1250-6.1 (300 USt), a Grove GMK6400 (450 USt), and a Grove GMK7550 (550 USt). 

Alvarez needed all that power because of the large size of the bridge spans, which required the three cranes to set the three sets of steel girders it took to achieve the appropriate length. Mike Lang, project manager for Alvarez Inc., said the cranes worked in tandem to pick and set multiple girders at a time. “To construct the bridges, each of the three cranes would pick up two side-by-side girders, for a total of six girders being placed at a time,” Lang said. 

This method gave the bridge the strength it needed while also allowing steel to be set quickly. “This bridge has a little bit of curvature on it,” Lang said. “The more radius of curvature a bridge has, the more steel you need to achieve stability.”

Girders were then spliced in the air by a team of up to a dozen ironworkers, effectively creating a single bridge piece from the three girders. Ironworkers got to the steel in a variety of ways. If it was possible to anchor one side of a girder to an abutment, they would tie off onto the steel itself. When that wasn’t possible, a man basket was employed.

The job required more than high-powered cranes, though. It needed human expertise in the cab. “Alvarez has used cranes from ALL exclusively for 20 years,” Lang said. “In that time, you also develop a comfort level with their crane operators. This was a complicated undertaking that required the operators to work in meticulous synchronization. Because we have that trust in their abilities, it made the entire job go that much smoother.”

The first crane would pick its sections, swing them into position, and hold. Next, the second crane did the same with its sections. At that point, the first set of ironworkers entered to begin the splicing process. Crane operators would adjust height as needed to line up the sections. After the first two sets of girders were spliced, the third crane would swing in its sections for splicing, completing a span.

The cranes had to perform a total of 35 of these triple lifts over the course of two weeks just to construct the first two phases of the I-79 bridge. The cranes moved through 1,100 tons of steel in that time. For phase three, the 450-USt Grove GMK6400 was able to bow out, and the remaining two cranes handled the work.

----------

Editor's Note: Scranton Gillette Communications and the SGC Infrastructure Group are not liable for the accuracy, efficacy and validity of the claims made in this piece. The views expressed in this content do not reflect the position of the Roads & Bridges' Editorial Team.

Related Articles

Excitement is buzzing in the “City of Oaks” and its surrounding communities with so much commercial and residential development. However, growth does…
December 24, 2019
Road and bridge construction jobs outpacing rest of construction world
Road and bridge construction jobs outpacing rest of construction world
According to a report by the Bureau of Labor Statistics, U.S. highway, street, and bridge contractors posted a total employment of 396,000 in June, a…
August 12, 2019
Mississippi DOT still dealing with Delta region flooding issues
Mississippi DOT still dealing with Delta region flooding issues
The Mississippi DOT (MDOT) crews are continuing to monitor the condition of flooded highways throughout the Mississippi Delta region. MDOT officials…
July 25, 2019
Scott Owyen, Genie Senior Training Manager, Terex AWP
Scott Owyen, Genie Senior Training Manager, Terex AWP
GENIE “ASK ME ANYTHING” EVENT TO ADDRESS NEW NORTH AMERICAN MEWP STANDARDS June 6, 2019—Genie is inviting customers to ask questions and get answers…
June 07, 2019
expand_less