Stringless paving takes off at N.C. airport

Nov. 9, 2010

The Charlotte Douglas International Airport in Charlotte, N.C., was named the eighth-busiest airport in the U.S. and the 24th-busiest airport in the world by passenger traffic in 2009.

As passengers from around the world flew in and out of the airport, Hi-Way Paving Inc. was slipforming a new 9,000-ft-long runway that would make the airport even more efficient and traveler friendly in 2010 and beyond.

The Charlotte Douglas International Airport in Charlotte, N.C., was named the eighth-busiest airport in the U.S. and the 24th-busiest airport in the world by passenger traffic in 2009.

As passengers from around the world flew in and out of the airport, Hi-Way Paving Inc. was slipforming a new 9,000-ft-long runway that would make the airport even more efficient and traveler friendly in 2010 and beyond.

No strings attached

Hi-Way Paving, based out of Hilliard, Ohio, was the prime contractor for the Phase II package of work at Charlotte Douglas. Concrete paving work included the new 9,000-ft-long runway, two taxiways that were 4,500 ft and 4,800 ft long, high-speed crossovers and four large connectors that tie into the existing runway. Approximately 242,500 cu yd of concrete was slipformed during Phase II, all with Hi-Way’s GOMACO paving equipment.

Hi-Way Paving brought in its GOMACO four-track GHP-2800 paver, PS-2600 placer/spreader and T/C-600 texture/cure machine. Since it was planning on paving around the clock at the airport, they added a new two-track GHP-2800 and PS-2600. Crews could be paving with one train during the day, while another crew could be setting up another train for a night pour.

Also new to Hi-Way Paving’s inventory for the airport project was a stringless paving system. The placer/spreaders were controlled by GPS units, while the pavers utilized total stations for greater accuracy.

In fact, the entire project was stringless, including the 6-in.-thick cement-treated base (CTB). Approximately 85,000 cu yd of CTB was laid on the airport, forming a solid base for the new concrete.

Concrete for the project was mixed on-site with two 12-cu-yd mobile batch plants. The concrete is an airport-approved, 650 flex mix design. Slump averaged between 1 and 1.5 in., depending on the day’s high temperature. Warmer days required a higher-slump concrete.

Dump trucks carried 10-cu-yd loads of concrete to the paving site and dumped onto the belts of the PS-2600s. Hi-Way’s new PS-2600 quickly earned the crew’s respect. Its larger conveyor pump and motor increased total conveyor power to 7,349-lb belt pull vs. 5,767-lb belt pull. Hi-Way also added the optional closed-loop augers, which provided 83 rpm vs. 34 rpm in auger speed.

On Hi-Way’s longer paving runs, both placer/spreaders were used in front of the four-track GHP-2800 to maximize production. The new runway is 9,000 ft long, 150 ft wide and 18 in. thick. The GHP-2800 slipformed it in six 25-ft-wide paving passes. Baskets were placed on grade every 25 ft to form each panel.

A new 75-ft-wide taxiway is situated parallel to the runway. The GHP-2800 slipformed it in two 25-ft-wide paving passes and then slipformed the outside lanes 12.5 ft wide over wire mesh reinforcing.

“From day one on this project, we used the stringless system,” said Kevin Stephen, job superintendent with Hi-Way Paving. “The first day was a little scary because we had nothing to check it to. We’re used to having a stringline there that we can measure from and see that everything is on line. We learned to check each day’s pour prior to paving day, just to make sure we didn’t have a bad grade. It helped us locate any bad spots in the CTB and that helped us avoid any bumps in the final concrete because of bad grade.”

The total stations from the stringless system helped Hi-Way locate the electrical cans in the concrete. A total of 3,400 electrical cans were paved over in the runway. Electricians needed to find them and then core them out. The total stations were used to mark and locate each can so the light fixtures could be attached.

The new two-track GHP-2800 spent the majority of the project slipforming the 700-ft-long high-speed crossovers. The two-track’s maneuverability and fast tracking speed, up to 122 ft per minute, was beneficial for getting to and paving the shorter runs.

“The two-track is easy to get around with, get in and out of those short paving runs, and allows us to pour closer to the joints,” Stephen said. “A second paving spread allowed us to have a crew getting the equipment in place and set up for the night pour while we were paving on the runway during the day. It allowed us to move from spot to spot so we didn’t have any downtime at all.”

Time was critical for the crossover pours. They had to be completed at night with the airport only allowing 51?2 hours of working time so the existing runway could be open again to plane traffic by 6:30 a.m.

“That was basically a project all by itself,” Stephen said. “We had a night crew working constantly. They slipformed over 20,000 cu yd of concrete, connecting the old runway to the new connectors.”

Very little finishing work was required behind the pavers. Finishers used a 16-ft straight edge, and the T/C-600 machine applied a burlap-drag finish. The airport required both a smoothness and an edge-slump specification be met on all of the concrete pavement, including fill-in areas and short paving runs.

“The straight-edge requirement was one-eighth of an inch between lanes with a 16-ft straight edge,” Stephen explained. “The runway smoothness was measured with a two-tenths blanking band. We had to be under 7 in. per mile, and everything was measured and counted in the final smoothness. We had areas on the runway that only measured a 3, and we didn’t have to do any grinding on any of our pavement.”

Hi-Way’s project contract required completion of their work by Dec. 15, 2009. The airport then asked if they could open the entire project by Nov. 1. Moving a deadline up by more than a month’s time could have been disastrous for some contractors, but not Hi-Way Paving. By early August they had already finished the major paving on the airport, with only 2,500 cu yd of fill-in work left to complete.

“We are very pleased with our equipment and just keep getting better and better with the stringless aspect of it,” Stephen said. “Low-production days, working on the crossovers and such, we only averaged about 1,500 cu yd. But, on the high-production days, we averaged between 3,500 to 3,800 cu yd with 5,000 cu yd our highest in a nine-hour shift. The paving went well and our equipment worked really smooth for us.”

Information for this article provided by GOMACO, Ida Grove, Iowa.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.