Stage Exit

April 9, 2007

The culvert on Sylvan Ave. was just one small part of a very large Texas Department of Transportation freeway expansion project constructed in multiple phases over several months. The original culvert design called for a double-barrel run of 20 ft x 12 ft, 156.5 ft long to be placed alongside an existing, dog-legged, 30-ft span CIP culvert structure constructed in the year 1934. There is very little headroom at this location (from 0 to 3.5 ft), ideal for a CrownSpan installation. Each three-sided bridge unit weighs 29.7 tons and are available in stands of 14-40 ft and rises of 3-12 ft.

The culvert on Sylvan Ave. was just one small part of a very large Texas Department of Transportation freeway expansion project constructed in multiple phases over several months. The original culvert design called for a double-barrel run of 20 ft x 12 ft, 156.5 ft long to be placed alongside an existing, dog-legged, 30-ft span CIP culvert structure constructed in the year 1934. There is very little headroom at this location (from 0 to 3.5 ft), ideal for a CrownSpan installation. Each three-sided bridge unit weighs 29.7 tons and are available in stands of 14-40 ft and rises of 3-12 ft.

However, Gilbert Texas Construction L.P., the prime contractor, discovered that they could remove an entire phase from the construction of the main lanes if they could construct a temporary access tunnel under the temporary main lanes of the freeway to move their equipment through during that phase of the project, so the revised plan was to use the CrownSpan units for a temporary bypass.

At first, the plan was to have Hanson Pipe & Precast redesign eight units to withstand 13 ft of fill, but, deciding crews could use the extra headroom for their heavy equipment, it was decided to use the CrownSpan units as originally designed and raise them up to grade by placing them on elevated footings that the contractor designed.

After the footings had been constructed, the first eight units were delivered during the night due to heavy daily traffic volumes and safety concerns. Units were delivered on their sides in order to lower their center of gravity.

The delivery of CrownSpan units to the project location began in October 2004, and after seeing daily traffic volumes of around 150,000 for about 15 months, the eight temporary units were relocated to their permanent location on Sylvan Ave. The culvert at Sylvan Ave. was subsequently completed during the summer of 2005.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.