LAW: The Contractor's Side

Dec. 28, 2000
In highway-construction bidding, rarely does a disappointed bidder overturn a decision by state or local government officials because to do so generally requires a finding that the officials exercised their discretion arbitrarily. While, in general, state agencies are required to award public works contracts to the lowest responsible bidder, that requirement is not absolute.
In highway-construction bidding, rarely does a disappointed bidder overturn a decision by state or local government officials because to do so generally requires a finding that the officials exercised their discretion arbitrarily. While, in general, state agencies are required to award public works contracts to the lowest responsible bidder, that requirement is not absolute.

In most states, the DOT can award the contract to another bidder in cases where it is determined that this action will better serve the state's interests, provided that the DOT sets down its reasons for the award to a contractor other than the lowest responsible bidder, and clearly describes how the state's interest is better served.

A Delaware case, Harmony Construction, Inc. v. State of Delaware Department of Transportation, 668 A.2d 746 (1995), illustrates a situation where the court determined that a DOT's decision not to award a highway-construction contract to the lowest bidder was arbitrary and capricious.

In Harmony, the contractor was found to be the lowest responsible bidder on Contract 03, a highway-construction project. It was also the lowest responsible bidder on four other Delaware DOT (DelDOT) state highway projects. DelDOT had concerns regarding Harmony's ability to perform all five contracts satisfactorily and directed Harmony to provide-in writing-a work schedule illustrating how it would proceed to perform all five contracts if they were awarded.

However, DelDOT did not instruct Harmony to assume a specific start-up date for purposes of preparing the work schedule. Additionally, DelDOT asked Harmony to submit payroll and equipment lists and the names of the superintendents who would be assigned to each project. When DelDOT subsequently decided not to award Contract 03 to Harmony but did award the company the remaining contracts, Harmony brought action to enjoin DelDOT from awarding Contract 03 to the second-lowest bidder.

During the trial, DelDOT presented four reasons for not awarding Contract 03 to Harmony: Harmony was a new company that had no track record with DelDOT; Harmony's proposed work schedule would be "unworkable" and awarding the company Contract 03 would result in "too much" work for the contractor to perform; Harmony's equipment was titled to two other companies in addition to itself, compromising Harmony's ability to perform Contract 03 since the equipment could potentially be pulled off the job; and the same person would be acting as superintendent of Contract 03 and one of the other DelDOT contracts awarded to Harmony.

The court determined that only the second reason, the workability of Harmony's proposed schedule, played a significant role in DelDOT's decision. The remaining reasons had no credibility, especially in light of DelDOT's decision to award the four other contracts, all pertaining to road construction, to Harmony.

The court pointed out that, after DelDOT concluded that Harmony's start-up dates were unrealistic, the department assumed different start-up dates and developed a revised work schedule, which it did not share with Harmony. DelDOT further concluded that there would be overlaps between certain of the four other contracts that would ultimately prevent Harmony from satisfactorily performing Contract 03.

Referring to Delaware case law, the court explained the term "arbitrary and capricious" as actions that are unreason- able or irrational, or that are unconsidered or willful and not the result of a winnowing or sifting process. In other words, the term means action taken without consideration, and in disregard of the facts and circumstances of the case.

The court stated that, in this instance, it was DelDOT's responsibility to show the existence of a decision-making process rationally designed to uncover and address the available facts and evidence related to the issue to be decided.

Here, the court noted, DelDOT had no established rules or procedures to guide its representatives or the contractor in making a determination of this kind. Rather, DelDOT made the rules up as it went along, never told Harmony what they were, and only after the game was over was Harmony told it had "flunked."

This case is obviously unique. However, it points out that when the low bid is rejected, the state or local government should have a good reason for the rejection.

Parvin is a shareholder in the law firm of Leonard, Hurt & Parvin, P.C., which has offices in Dallas, Houston and Austin, Texas; Washington, D.C.; and Richmond, Va. Leonard, Hurt & Parvin engages in many specialties affecting the construction industry, including litigation, alternative dispute resolution, preparation and analysis of contract claims, partnering facilitation, environmental law, employment law, project financing, and disadvantaged business enterprise. You may write him in care of the editor.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.