Finding the Space for It

March 21, 2002

The Kentucky Transportation Cabinet (KYTC) used an unbonded overlay project on I-265, the Gene Snyder Freeway, as a testing ground for new methods, designs and specifications—most notably a new QA/QC specification.

The challenging two-mile project included large penalties/incentives, high traffic volumes, traffic maintenance on 16 ramps and a tight work area. Contractor Gohmann Asphalt and Construction Inc., Clarksville, Ind., completed the job ahead of schedule.

The Kentucky Transportation Cabinet (KYTC) used an unbonded overlay project on I-265, the Gene Snyder Freeway, as a testing ground for new methods, designs and specifications—most notably a new QA/QC specification.

The challenging two-mile project included large penalties/incentives, high traffic volumes, traffic maintenance on 16 ramps and a tight work area. Contractor Gohmann Asphalt and Construction Inc., Clarksville, Ind., completed the job ahead of schedule.

The project won an Excellence in Concrete Paving award from the Ohio-Kentucky Chapter of ACPA, and was a finalist in the national ACPA awards competition.

Reaching a new beginning

According to Robert Harris, KYTC district construction engineer, the existing concrete road had numerous cracks, joint faulting and severely deteriorated ride quality.  “It had reached the end of its useful life,” he said.

KYTC decided to explore a concrete solution. “Kentucky has traditionally rehabilitated concrete pavement with asphalt overlays,” said Harris. “It’s just been in recent years that the department is evaluating the concrete alternative.”

The design called for 9 in. of plain concrete on an open-graded asphalt bond breaker with staggered joint spacing (12 to 18 ft). The contractor used Type C fly ash as a partial cement replacement to assure the pavement was open to traffic quickly and economically. They replaced the existing asphalt shoulders with full-depth concrete.

A contract to speed

This project featured A+B bidding, an innovative contracting method that is becoming more common on KYTC’s high-profile projects. “We use it on our fast-in, fast-out jobs,” said Harris. Harris knew this project would attract a lot of attention. “The last third of the construction involved interstate-to-interstate traffic movement in an area of heavy industry and development,” he said.

Heavy penalties/incentives reflected KYTC’s need to complete the job as quickly as possible. They levied a $10,000 per day penalty/incentive for meeting the completion date and $25,000 per day road user cost/benefit for every day the permanent lane closures were more or less than the number of days specified. Gohmann received 100% of the maximum user-cost incentive.

Another innovative aspect of the project was the use of the QA/QC specification, a first for KYTC. “This was our infant version of QA/QC,” said Harris. “We wanted to see if it was workable. We tweaked it, and it’s working well—so well, in fact, that it’s going to become standard procedure next year.” The specification involved statistically evaluating strength and air content based on a percent-within-limits criterion. Gohmann received 95% of the possible incentive payment under the QA/QC spec.

One is enough

Traffic maintenance was truly a challenge with work-zone traffic at 50,000 vehicles per day. The contractor had to maintain traffic on 16 ramps in three interchanges. KYTC proposed running traffic on one side of the divided highway while working on the other side. This plan required 38 separate phases of concrete paving with numerous temporary median crossovers. “With 16 ramps in a 2-mile stretch, the original plan was too complicated,” said Joel Field, concrete paving division manager for Gohmann.

The contractor proposed constructing one lane at a time to simplify the complicated traffic maintenance scheme. This plan reduced the number of phases to two and eliminated all temporary median crossovers. KYTC accepted the proposal, looking to provide increased safety and convenience for motorists. The less complex plan also saved approximately $125,000.

“The department had always felt it would be best to remove the traffic completely from the construction zone. But the contractor felt our traffic maintenance plan would be unworkable; he wanted to do everything behind one-lane closures,” said Harris. “He proved he could do the job under traffic.”

Working behind concrete barriers with only 18 in. of clearance, Gohmann needed to do some creative thinking. To fit the equipment into this tight area, they used a high-drive track and unique mechanical tie-bar inserter on the slip-form paver, plus custom-fabricated string-line holders. This was one of the first times the high-drive track, manufactured by Gomaco Corp., was used in the U.S. Gomaco also custom made the tie-bar inserter for this project to pull the 30-in. bent tie bar into the side of the new pavement.

“The most innovative part of this job was being able to perform paving with a small clearance close to traffic,” said Field. “We had 2 ft and then a vertical wall.” He feels one-lane-at-a-time construction will benefit the concrete paving industry. “It puts concrete on an equal level with asphalt,” he said.

In addition to equipment modifications, Gohmann introduced a couple of paving methods KYTC had not yet seen. Although standard for Gohmann, dual string lines of braided aircraft cable were new to KYTC. “The cables gave them a better shot at rideability,” continued Harris. “We hadn’t seen string lines like that before.” The contractor also used an early entry saw, which Harris said was new to them, “It allowed them to get on the slab earlier and reduced random cracking.”

Nice balance

Harris deemed the project a success. “We accomplished our objectives, with the QA/QC specification being the most positive outcome,” he said. “The project showed concrete can be put down under heavy traffic in a confined space.”

The main challenge of the project, according to Field, was to “balance quality issues with time and construction problems.”  He added, “We worked out the optimal balance.”

Field feels this project will have an impact on future paving decisions in Kentucky. “I hope it opens the door to additional opportunities for concrete pavement,” he said. This project has changed the thinking about what can be done, and gives owners more options.”

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.