2011 Top 10 Roads - No. 3

Nov. 8, 2011
Sometimes change is good - Maryland road project designer tweaks initial plan to trim costs, reduce environmental impact
PROJECT: Intercounty Connector—Contract C
LOCATION: Montgomery and Prince George’s counties, Md. 
OWNER: Maryland State Highway Administration
DESIGNER: Dewberry
CONTRACTORS: ICC Constructors, a joint venture between Shirley Contracting Co., Clark Construction, Atkinson Construction, Facchina Construction Co. and Trumbull Corp.
COST: $525 million
START DATE: April 2008
COMPLETION DATE: November 2011
The designer of a road construction project on the Intercounty Connector (ICC) in Montgomery and Prince George’s counties, Md., was able to adapt the original plan to 
better suit the environment and save money by using engineering innovation to solve problems with existing natural conditions.
 
The project’s original design went through an “alternative technical concept process,” in which each of the design-build teams can propose ideas to modify the plan. Dewberry, the designer, pitched an idea that would recon?gure the interchange by reducing the number of ? yover ramps—and save about $75 million.
 
The main alignment approaching I-95 was near an old quarry, with many wash ponds in the area. 
 
“We ended up realigning the mainline of ICC to the south a few hundred feet, allowing us to avoid some of the adjacent wash ponds and provide a different interchange con?guration, thus avoiding a large amount of bridge structures,” Dave Mahoney, the project manager, told ROADS & BRIDGES.
 
The state’s original design placed bridges over those wash ponds, which Mahoney said were 40-50 ft deep and contained sediment from the gravel-pit operations.
 
“We used wick drains to slowly ? ll in those wash ponds and pull the water vertically out of the material, dry the material and turn it into an embankment for the roadway,” Mahoney said. “We avoided the need to build long bridges with very deep foundations to reach the bottom of the wash ponds as well as the need to ? nd material to set the bridge in. That was a real strategy, to improve that area instead of building a bridge.”
 
The realignment of the interchange and use of wick drains helped to reduce the bridge structure area by more than 200,000 sq ft. Originally, 29 storm-water-management ponds would have been affected by the design; after redesigning and rerouting drainage, only 14 ponds were affected, reducing impact to the surrounding property owners and the environment.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.