20-year-old Illinois tollway includes 24 bridges needing rehab
Bridge repair work is scheduled to begin on Monday, May 17, as part of the Veterans Memorial Tollway (I-355) Roadway Resurfacing & Bridge Repair Project between the Reagan Memorial Tollway (I-88) and Army Trail Road and between I-55 and 75th Street.
Work to repair and maintain the 20-year-old I-355 roadway began in April and continues through fall, including rehabilitation of 24 bridges with structures in both directions along the corridor.
The first bridges scheduled for work include the Tollway ramp bridge carrying traffic from northbound I-355 to westbound I-88, Finley Road bridge over both I-88 and I-355 between Ogden Avenue and Lacy Drive, the 75th Street Bridge over I-355 and the Tollway ramp bridge carrying northbound I-355 traffic to I-88.
The repair work is part of the Illinois State Toll Highway Authority’s Congestion-Relief Program—Open Roads for a Faster Future—and includes improvements in coordination with DuPage County. Construction will affect traffic on the tollway as well as local roads.
I-355 Northbound Ramp Tunnel to Westbound I-88
Traffic shifts in the ramp tunnel carrying traffic from northbound I-355 and Ogden Avenue to westbound I-88 will begin at approximately 7 a.m. on Monday, May 17, and will continue for two months to accommodate repairs. Repair work includes expansion joint replacement, partial-depth repairs and placement of a new, 4-in.-thick reinforced concrete surface. The speed limit on the ramp will be reduced to 40 mph from 50 mph.
Finley Road Bridge Repairs
Traffic on Finley Road will be reduced to one lane in both directions between Ogden Avenue and Lacy Drive beginning at 7 a.m. on Monday, May 17, for approximately three months as the Illinois Tollway makes repairs on the DuPage County bridge carrying Finley Road over I-88 and I-355. Repairs include removal and replacement of expansion joints, installing a new drainage system, constructing retaining walls and repairing a slope wall. Delays are expected.
75th Street Bridge Repairs
In order to minimize the impact to traffic on high-volume bridges, work on the DuPage County 75th Street Bridge over I-355 will be scheduled over two weekends, Friday, May 21, to Monday, May 24, and Friday, June 4, to Monday, June 7. Lanes will be closed and traffic shifted on the 75th Street Bridge to complete work over the first weekend on the inside lanes and turn lanes, including partial-depth concrete repairs and slope wall work. Work in the outside lanes of the bridge will be completed on the second weekend. No work is planned on Memorial Day weekend, May 28-31.
Mainline Tollway bridges scheduled for repairs include Jackson Drive, Ogden Avenue, Finley Road, 22nd Street, Foxworth Boulevard, Oak Creek Drive, Roosevelt Road, IL Rte. 53, Fullerton Avenue and Army Trail Road.
Crossroad bridges over I-355 scheduled for repairs include 75th Street, 71st Street, Warrenville Road, Finley Road, Butterfield Road, Hill Avenue, Union Pacific Railroad, Crescent Boulevard, St. Charles Road, Pleasant Lane and North Avenue.
More information is available at www.illinoistollway.com in the Construction Section and at 800.TOLL.FYI.
More like this
- Ground broken for Naperville Road Interchange improvements in Ill.
- Illinois Tollway announces construction projects for Reagan Memorial Tollway
- Illinois Tollway announces 2012 construction program
- Southwestern Chicago tollway promises major changes
- Illinois Tollway debuts Open Road Tolling in DeKalb/Dixon area
Roads&Bridges Videos
Products
8049 Products
-
The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format. The FVT/...
-
RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
-
Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
-
Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
-
JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
-
Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
-
The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
-
Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
-
The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
-
Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...