Printer-friendly versionSend to friend
Tuesday, April 15, 2003 - 11:28
Right away

Strong partnerships lead to quick decisions when time is sacred

What's behind the newfound urgency in restoring roadway
infrastructure?

How is it decided that a heavily damaged, three-span
interstate bridge can be completely rebuilt in 47 days?

Or, how does a state highway department get away with closing
5 1/2 miles of heavily traveled interstate completely for two consecutive
weekends to speed up a repavement project and then get praised by the traveling
public for doing so?

And how did the urban interstate bridge that suddenly and
mysteriously cracked during the middle of winter get rebuilt in a little under
seven months?

What made all of this happen, in an industry known for
schedule overruns and multi-year construction projects?

Nowadays, the huge increases in traffic demand that
damaged or destroyed infrastructure be back at work in the shortest possible
time. And the time lost while repairing a bridge or highway represents real
money; in some cases millions of dollars a day while the structure is out of
commission. These factors have ushered in the age of accelerated reconstruction
of damaged or destroyed pieces of America's infrastructure. So what's making
all of this possible?

It's a whole new way of looking at highway
reconstruction, ranging from the use of design-build contracting techniques to
innovative financing that makes funds available faster to using newer
construction methods and materials that speed up the completion of the project.
In one case, it was simply a matter of improving communications.

But the glue that is making the whole thing work is the
close partnerships and working relations that the states, communities,
contractors and the federal government have forged. And some of the initiative
has come from the Federal Highway Administration (FHWA) in its role as a
pioneer in transportation, breaking the mold and promoting business not as
usual.

In the last few years this has all come together,
resulting in the record restoration times of structures. Workshops have been
held around the country to document and inform the highway community of the
logistics and mechanics of all this information.

Here's how three different state highway departments
dealt with three different infrastructure reconstruction problems, each with
it's own peculiar circumstances; one a vital commercial interstate link, the
second with a potentially large public relations problem and the third
dependent on the successful identification of structural failure.

Bypassing bureaucracy

A classic example of bypassing the normal bureaucratic way
of doing things occurred when a bridge on I-40 in Oklahoma was destroyed in May
of 2002 by a string of barges that had drifted off course on the Arkansas
River. Fourteen people lost their lives in this tragedy.

Not only was there a loss in human life; there was a
potential loss of $430,000 a day for the bridge's users.

I-40 is one of the transcontinental interstates that
cross the country. It begins in Wilmington, N.C., and terminates in Barstow,
Calif., and carries a tremendous amount of commerce and travelers; this
particular bridge carried about 20,000 vehicles a day.

Within one hour of the tragedy, FHWA Oklahoma Division
Administrator Walter Kudzia and his Assistant Division Administrator Lubin
Quinones were on the phone with their counterparts in the Oklahoma state DOT
(ODOT), discussing how they could help the state move quickly to repair the
span. At the same time that morning, the ODOT Chief Engineer (Get name.) was
arriving at the scene. Because of the circumstances, he stayed on for several
days.

Once it was determined that the cause of the collapse was
an accidental collision and not an act of terrorism, detours were established
and opened so that delay to traffic was kept to a minimum.

Kudzia and Oklahoma Director of Transportation Gary Ridley
then met to decide how to structure the bidding to get the bridge restored as
quickly as possible.

"I pushed for A+B bidding with
incentive/disincentive provisions and greatly reduced bid response times,"
said Kudzia. "I stressed that this was an emergency situation and normal
procedures in designing and replacing the spans would not be appropriate."

The contract time, in hours, however, was determined by
Ridley and his staff, using a critical path methodology.

A rare prebid meeting was held just a week or so after
the collapse at the bridge site so potential contractors could see the extent
of the damage. At the same time, ODOT
decided to tap funds normally only available for scheduled and approved
projects to get the demolition and construction underway immediately. They
would be replaced later with emergency funds, which take longer to make their
way through the bureaucracy.

FHWA's Kudzia concurred.

A contract was let to design the new spans at the same
time demolition of the damaged spans was taking place. The contract called for
the design to be complete in 16 days; it was actually completed in 12 days.

A short list of qualified bidders was drawn up and the
bidders were given just four days to return their bids; the normal time for
returning bids would have been 21 days. At the end of the four-day period, the
bids were opened, the low-bidder selected and the recommendation made to the
Oklahoma Transportation Commission, who approved it the same day.

In other words, in less time than it would have normally
taken to put a project out for bid, wait the 21 days to receive the bids,
select the winner and award the contract, the I-40 bridge project was designed,
the damaged structure removed and a contract for its replacement awarded. Total
elapsed time: 18 days.

While the project was completed ahead of schedule, the
contractor was sufficiently motivated to do so. His reward was $1.5 million in
incentives. But it was the intense and in-depth relations between the
governmental agencies and the contractor which made the project happen.

Shut it all down

How can closing an interstate be justified in the face of
a daily traffic count in excess of 85,000 vehicles?

The answer is obvious, when the alternatives to
accomplishing this repaving project add up to more inconvenience to motorists
and neighboring communities, numerous safety concerns and significant negative
emergency response and economic and transit impacts.

This was the dilemma facing the Washington Department of
Transportation (WSDOT) when they addressed the repaving of a 5 1/2 mile section
of busy I-405. Busy is the right word for this section of the highway; it is
the main north-south bypass around Seattle.

It all started two years prior to the actual paving
operation, in 1995, when WSDOT staff met with municipal officials of the cities
that were adjacent to the section that needed to be repaved. The staff
presented officials with a matrix that described several different approaches
to accomplishing the work, including one that had the work being done during
nighttime hours, an approach that would have taken an entire construction
season. Other options included day work and partial weekend closures. The
approach that made the most sense from being least intrusive on the motoring
public and the neighborhood communities was a total freeway closure over two
weekends.

This approach offered several additional advantages:

_ It was the
least expensive;

_ It offered
the best possible finished product in terms of quality; and

_ It
promised motorist and worker safety.

But the prospect of closing the interstate, even at
nights on weekends, posed a huge public relations problem, both for WSDOT and
the neighboring community populations. It was decided to employ every possible
means of communications to let everyone know what was going to happen.

For its part, the local media were very supportive by
providing detailed information to the public. WSDOT public information staff
mounted a major public relations program, making the construction engineer as
well as public information personnel available for interviews. But that was
just the beginning. Communication and coordination continued with the local
cities throughout the entire construction period. Advance notice to the media
had already begun in the spring of 1997 with additional reminders given out one
month before the closings. Variable message signs with detailed information on
the closures were installed two weeks prior to the closures. This was followed
by detailed news releases and phone calls to targeted radio and TV stations.
WSDOT also provided internet postings, telephone hotlines, community fliers and
various other communications methods.

Two weekends were selected in August, the month when the
weather is driest. An eight-mile section of southbound I-405 was closed from 8
p.m. Friday night until 5 a.m. the following Monday. The process was repeated
the following weekend with the northbound section.

In spite of the potential for massive disruption, the
freeway closures and construction work went well. The contractor met all
schedule and quality expectations. The partnering work with the contractor was
important to ensure all issues were addressed and resolved in advance.
Particularly crucial was the haul route, which the contractor innovatively
reduced by arranging with the Boeing Co. to temporarily lease a nearby parking
lot to stockpile material and set up a portable hot-mix asphalt plant. The
proximity of the plant was an enormous benefit.

An unexpected benefit came out of the project; increased productivity.
Production rates for applying hot-mix asphalt averaged 350 tons/hour as
compared to a normal 205-313 tons per hour for night paving on comparable
projects.

Cracking up

The City of Milwaukee, Wis., is used to cold
temperatures. So when the temperature dropped to 4 degrees below zero on the
morning of Dec. 13, 2000, most folks went about their business as usual.

Except those who were driving across the Hoan bridge, on
their way to work. Just before the rush hour, a 100-200-ft section of the bridge cracked from top to bottom, causing a
sag in the northbound lanes about 200 ft from the bridge's edge. One person,
who was on his way to his job at about 6:30 a.m., said that he noticed the
sudden sagging a little bit. "It felt a little different. I thought maybe
there was a pothole forming," he observed.

The bridge was once dubbed the "Bridge to
Nowhere" because even though the structure connected the lakefront's north
shore with its south shore, it fell far short of its envisioned use. But on
that day, the bridge was carrying in upwards of 37,000 vehicles a day. Experts
predicted it would take over a year to repair. One local official said that was
far too long, claiming that the bridge is a lifeline to local communities.

So the urgency of getting the bridge back to working
order was established. But that couldn't happen until the reason for the
failure was established.

"Was it the Welding? Was it the Steel? Was it the Cold? Was it the Traffic?
Was it the Soils?" asked a headline in the Milwaukee Journal newspaper.

"The driving force that controlled this was the
desire to get the bridge fixed as soon as possible," said Tom Strock,
Structural Systems Engineer with the FHWA's Wisconsin Division. "We
accelerated the failure analysis. We also wanted to propose an interim 'fix';
something that could possibly prevent further cracking. We called this a
'prophylactic retrofit', a procedure whereby a series of 2,000
holes would be drilled in the surviving beams. The holes would prevent
the spreading of any subsequent cracks developing."

A contractor was selected and the work was performed on
Jan. 16, 2001. Work was accelerated so that at least two lanes on the
southbound span could be opened as soon as possible.

"There was also the urgency to get the material from
the failed beams into analysis to find out why they failed," continued
Strock. "This had to be done so we could make sure that what we were
replacing would not be subject to the same failure."

A meeting was scheduled with the Senate/House transportation
committee on Jan. 18 to give them a briefing on what was being proposed.
"It provided the local government folks an opportunity to tell the
legislators how important the bridge was to the well-being of Milwaukee and the surrounding areas.
Eventually, they went along with our recommendations," Strock added.

Unfortunately, during the course of the hearing, another
crack appeared, this one about 7 ft long. As approval for the retrofit had
already been cleared a plate was bolted over the newly formed crack. "As
luck would have it, during the bolt-on process another crack appeared, sounding
like an explosion," commented Strock. "When we looked over to see how
far the crack had spread, we saw that it been stopped by the drilled holes. In
other words, our prophylactic retrofit had functioned as we predicted it
would."

An additional briefing was given to the Governor and the
Secretary of Transportation on Feb. 16 to describe how the retrofit had worked.
Everyone now agreed that the south span was probably safe for limited,
low-speed passage. Accordingly, on Feb. 17, the south span was open for two-way
traffic. A four-ton limit on vehicle weight was imposed and trucks were
prohibited. All of these restrictions were precautionary in nature; no one felt
that the span was unsafe.

Meanwhile, the analysis had proceeded, but initially it
started off on a wrong supposition--that the problem was one of fatigue. There
were several groups involved in the analysis; FHWA's own Turner Fairbank
Highway Research Center, WisDOT, Lichtenstein Engineering, Lehigh University,
Northwestern University and Michigan Tech University.

Prior to the completion of the failure analysis, WisDOT
district engineers set upon a separate course to develop plans for a total
replacement of the three girder spans of the bridge, estimated to cost $40
million. "They even went ahead and selected a consultant to design the new
span," added Strock. "We urged them to hold off until the analysis
was complete and they agreed to wait."

The failure analysis focused on the global and localized
structure load paths and stress, extensive material properties testing and
detailed microscopic examination of the failure surfaces. The material
properties exceeded the requirements at the time the bridge was constructed and
most would meet current requirements. Therefore, the failure could not be
attributed to poor material. The findings of the failure analysis pointed to
the geometric configuration of the web, vertical stiffener and horizontal shelf
plates creating a zone of stress concentration and triaxeal constraint to a
very localized portion of the web plate. This combination of effects resulted
in a condition were the web was not physically able to yield under high stress
and initiated a brittle fracture from an uninspectable microscopic flaw. This
is the first time that this failure mode has been documented in a bridge
failure.

Once the failure mode was understood, the solution to
retrofit the remaining bridge became rather apparent. The structural analysis
showed that the bridge could be modified to function safely without the lower
lateral bracing connected to the horizontal shelf plate. The removal of these
items would eliminate both the stress concentration and the constraint
conditions which contributed to the failure. After receiving approval from
upper management, retrofit plans were prepared and a retrofit contract was
authorized using Advanced Construction (AC) funds. All this happened in just 16
days from the agreement on the failure mode. The use of AC funds allowed the
project to proceed without delay of trying to identify additional funding
sources. The final retrofit project restored the bridge to full unrestricted
traffic on Oct. 11, 2001, at a cost of just $7.5 million. This effort resulted
in a substantial savings in both time and money over the total replacement
solution.

On March 25, 2002, U.S. DOT Transportation Secretary Norm
Mineta presented a symbolic $12 million check to Gov. Scott McCallum to help
offset the total cost of the Hoan Bridge failure. Mineta's presentation, which
took place overlooking the Hoan Bridge, was a fitting tribute towards the
exemplary teamwork of everyone involved with and affected by the unexpected
failure of the bridge on Dec. 13, 2000.

Fastest way to go

The above three accelerated construction projects are
just representative of this trend that is occurring across the country. For
example, accelerated paving projects that usually allow a total closing of the
section of highway to be repaved/rebuilt/rehabilitated have been successfully
completed in Detroit, Mich., Wilmington, Del., Louisville, Ky., Portland, Ore.,
and Columbus, Ohio. In the Columbus project, the section of I-670 to be rebuilt
expanded the road from four to eight lanes and reduced construction time from four
years to 18 months.

Of the wisdom of shutting down this entire section of
I-670, Gordon Proctor, director of the Ohio Department of Transportation said,
"Under the appropriate conditions, a full closure can be an effective way
to complete projects faster and improve highway safety for highway workers and
motorists."

And in Birmingham, Ala., in January of 2002, a tanker
truck struck a bridge support at the junction of I-65/20-59, a critical
juncture that carries about 140,000 vehicles a day. While this interstate
intersection was out of commission it was costing the state at least $100,000 a
day in user costs. Through an extraordinary partnership between the state DOT,
the FHWA and the contractor, the bridge was able to be replaced just 53 days
after the crash occurred.

It does appear that accelerated construction is here to
stay.

Using innovative techniques and creative thinking, the
accelerated construction approach has proven to be a viable solution for the
construction of today's complex, multiphase urban projects. States like Indiana
and Pennsylvania have already benefited from employing this concept. A number
of other states have recognized its potential as well and are preparing to
employ it in the near future. FHWA and the Technology Implementation Group of
the American Association of State Highway & Transportation Officials
(AASHTO) have unified efforts to advocate and promote the accelerated
construction approach. For more information on the FHWA/AASHTO Accelerated
Construction Program, please call Dan Sanayi at 202/493-0551; e-mail:
dsanayi@fhwa.dot.gov, or Jim
Sorenson at 202/366-1333; e-mail: james.sorenson@fhwa.dot.gov.

Roads&Bridges Videos

 

Industry News

The Ohio Department of Transportation (ODOT) is hoping to generate millions of dollars in new money by launching a program that will permit...
As the people in and around Atlanta prepare to decide on a sales-tax referendum that could generate $6.14 billion for transportation upgrades,...
Utah’s S.R. 92 project should have been completed in late 2011, but traffic cones are still visible. Now the state legislature is telling the Utah...

Products

8968 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...